January 13, 2023
In the near future,Frequent supportive policies for wind power industry,Centralized landing of good news,The major wind farms are also good news.。Since December 2022,The performance of Zoomlion crane is outstanding.,Demonstrate strong strength on the land of Shenzhou。
Beian No.5 Wind FarmBArea 200MWProject
31 December,With the precise docking of the fan impeller with the cabin at an altitude of 100 meters,,Anbei No.5 Wind FarmBThe first Wind Turbine of the district project——BX03#Successfully completed the hoisting work of the Wind Turbine。
▲Beian No.5 Wind FarmBArea 200MWWind Turbine head crane
There are many procedures for this hoisting.、Difficult、The risk factor is high。To ensure the successful completion of the hoisting task,All the staff are cohesive、Walk in the same direction。It took 70 hours to fight.,Successfully complete the hoisting task。Excellent performance of Zoomlion Crawler Crane in the lifting process,The hoisting task was successfully completed.。
Salt pond beach 100MWWind power project
December twenty eighth,WithZX02 The precise docking of the wind turbine impeller and the nacelle is completed at an altitude of 100 meters.,Gansu Power Investment Jiuhui Company Gaotai Yanchitan 100 MW Wind Power Project Successfully Completed the Hoisting of 30 Wind Turbines,It marks that the project has entered the countdown stage of grid-connected power generation.。
▲Gaotai Salt Pond Beach 100MWWind turbine hoisting for wind power project
After the completion of the project, it is estimated that the project will provide about 2% of the electricity to the power grid every year.800 million kilowatt hours,Save about 90000 tons of standard coal,Reduce CO2 emissions by about 23 percent.80,000 tons。
China Nuclear Iron Gate Close 200MWWind power project
November twenty fifth,CNNC Tiemenguan 36th Regiment 200MWSuccessful completion of wind turbine hoisting for wind power project,It marks a phased victory in the construction of the project.。
▲China Nuclear Iron Gate Close 200MWWind turbine hoisting for wind power project
During the construction of the project,The project department always insists“Safety first、Quality-oriented”The purpose of。In order to complete the construction task on schedule,Project staff often work late into the morning.,Finally, with the joint efforts of all staff,,Successfully completed the hoisting operation of all 40 wind turbines。
Inner Mongolia Tanghe Project Lanqi Wind Power Project
December 24,Zoomlion Crane in Lanqi Wind Farm of Tanghe Project in Inner Mongolia,Completed the hoisting task of the first 140-meter all-steel segmented tower unit in China。
▲Wind turbine head crane of all-steel segmented tower project
The wind turbine hoisted this time is the first set of 140-meter all-steel segmented tower unit independently developed and manufactured by Shandong Wind Power Company of Zhongche Qiche Group.、It is also the first set of split tower of CRRC.。
Yunnan Julongliang Wind Power Project
December 20th, 17:00 p.m.,Julongliang Wind Power Project in Yunnan(Phase I)Project construction site,6 with the largest single capacity in the country.Successful hoisting of 7 MW plateau mountain wind turbine,The diameter of the fan impeller hoisted this time has reached 191 meters.,It has refreshed the world record of wind turbine construction in plateau and mountainous areas.。
Participated in the construction ofZCC13000 Crawler Crane,Unit capacity of the first hoisted No.1 wind turbine 6.7 MW,Hub height 115 m、Blade length 93 m、Engine room weight 138 tons、Impeller diameter 191 m。It is the largest single unit capacity in China at present.、The tower has the highest height、The longest impeller diameter of the plateau mountain fan。
Guangxi Tianlin Lucheng 150MWWind power project
December 16,Guangxi Tianlin Lucheng 150MW Wind Farm Project First 6.Hoisting of 25MW wind turbine Generator completed,It marks the successful hoisting of the first largest single alpine wind turbine in Guangxi.。
▲Guangxi's First Most Continental Wind Turbine Successfully Hoisted
Hoisting this timeWUnit capacity of No.31 fan 6.25 MW,Wheel hub height 110m,Impeller diameter 182 m,Maximum lifting capacity 160t,It is the largest single unit capacity of alpine wind power completed in Guangxi at present.、The leaves are the longest、Fan with the largest lifting capacity。
Huaneng Jilu Da'an City 500MWWind power project
December eleventh,With the precise docking of the last fan impeller and hub at an altitude of 100 meters,,Huaneng Jilu Da'an City 500MWThe hoisting of 25 wind turbines in the wind power project was successfully completed。ZoomlionZCCThe 13000 Crawler Crane is used as the main crane。
▲Huaneng Jilu Daan 500MWWind turbine hoisting for wind power project
The total installed capacity of the project is 500 MW.,Construction of single unit capacity 3.69 units of 65 MW wind turbines with a single unit capacity of 5.50 0 MW wind turbines。The project is completed and put into production,The estimated annual power generation is 16.100 million kilowatt hours,Effective replacement of standard coal 48.30,000 tons,Carbon dioxide reduction 125.60,000 tons。
Mu Lei 40 Jing Zi 800MWWind power project
December seventh,It is the heavy snow solar term,Mulei Kazakh Autonomous County in Xinjiang is already snowy.,Heaven and earth are covered with snow and beautiful.。ZCC9800WCrawler crane and all the staff braved the wind and snow.,Seize the short window period,The hoisting of the wind turbine is completed.。
▲Wind Turbine Hoisting of Mulei Forty Wells Wind Power Project
The hoisting of 6.7 MW wind turbine,Wind turbine hub center height 110m、The equivalent of a 30-story building.,Blade length 93 m、Engine room weight 134 tons。After completion, it will become an integrated wind farm with the largest single unit capacity.。2023,Wind power industry or will usher in a new“The rush to install”。“A workman wants to do his work well.,You must first sharpen your tools.”,The vigorous development of wind power industry can not be separated from the strong support of construction machinery and equipment.。“Where there is wind, there is Zoomlion.”,Zoomlion Crane will continue to create the best products,Escort Wind Power Construction in China。
December 11, 2024,Dongfeng Commercial Vehicle 2025 Annual Partner Conference Held in Chengdu。Based on the final season of 2024,Dongfeng Commercial Vehicle joins hands with more than 600 dealers nationwide、There are more than 1000 representatives of mor
December eleventh,With“WE ARE ONE——A family、One heart、Work together、It's going to work”The 2025 Global Supply Chain Strategic Partnership Conference of China Heavy Truck Group was held in Shandong International Convention a
The other day,Final judgment of the People's Court of Changsha County, Hunan Province,It was found that Anbaituo Trading Co., Ltd. had caused damage to the commercial reputation of Sunward Intelligence.,Its behavior constitutes unfair competition.
December 2,Beijing Party Branch of International Corporation and Construction Machinery Party Branch of China Construction Machinery Corporation、The General Party Branch of China has launched“Forging New Productive Forces and Promoting New Indust