Recently,In Dechang County, Liangshan Prefecture, Sichuan Province,Accompanied by the precise docking of the first fan impeller with the cabin at an altitude of 110 meters,First Wind Turbine of Labashan Wind Power Project Successfully Completed Hoisting,It marks a new breakthrough in the first batch of large-scale wind power and photovoltaic base projects in the country.,Zoomlion Crawler Crane participated in the whole process,Once again prove extraordinary strength with perfect performance。
Labashan Wind Power Project is located in high mountains and valleys.,The terrain is undulating and the altitude is very different.。The hub center of the Wind Turbine installed this time is 110 meters high.,The engine room weighs 122 tons.,Impeller diameter 172 m、It weighs 110 tons。It is the windy season at present,Engineering construction is facing great difficulty in hoisting.、There are many difficulties such as high risk and very short effective construction window.。Huge size of Wind Turbine equipment,But it has to be assembled on a narrow hilltop platform.。
The tower and nacelle of the fan in the blade yard can only be used when the wind speed is less than 10m/sIt can only be hoisted under the condition of。Because that wind area of the blade is lar,,Hoisting conditions are more stringent.,Wind speed must be less than 8m/s。At the first stand,Every day, the wind speed is less than 10 for only a few hours from dawn to dawn.m/s,Wind speed is less than 8m/sThere are even fewer time slots.,The operation efficiency and stability of lifting equipment are severely tested.。Take advantage of performance and design,Zoomlion Crawler Crane became the best choice for this task.。
Completion of hoisting of the first unit
Fan installation recordsTower hoisting
Engine room hoisting
Lifting of blades
Hoisting is completed
According to the plan,Yalong River Basin Water-Wind-Solar Complementary Green Clean Renewable Energy Demonstration Base,Total scale exceeds 80 million kilowatts,It is planned to build 60 wind turbines.,After completion, it will become one of the largest green and clean renewable energy bases in the world.。
Successful hoisting of the first wind turbine,It marks that the installation of mechanical and electrical equipment of Labashan Wind Power Project has achieved a phased victory.,Accumulated valuable experience for subsequent fan hoisting,It also laid a solid foundation for power generation on schedule in 2023.。
Video、Pictures, etc. From:Yalong River Hydropower Culture
Several XCMG climbing platform fire engines with a total value of more than 10 million yuan lined up to go overseas with surging momentum.,Protect the beautiful world In recent years,XCMG Fire Fighting for High-rise Rescue、Industrial
November nineteenth—22nd,Secretary of the Party Committee of the company、Chairman Peng Zhengyong led a team to Xinjiang to carry out a series of business activities,Visited the Xinjiang Autonomous Region Highway Development Center respectively.、X
bauma CHINA 2024(Shanghai BMW show)Will be November 26-The curtain was raised at the Shanghai New International Expo Center on the 29th.!Wirtgen Group will bring Wirtgen、Fogler、Humvee、Kelei's Four Brands Appear at the Exhibition,Showcase innovativ
When the north wind passes through,The most romantic thing is a night of spring breeze.,It was delivered.“To turn thousands of pear trees here in full bloom white.”A grand scene。However,Behind this beauty.,With the increasing use of tr
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China