Zoomlion: Fuyuan West Wind Farm Connected to the Grid for Power Generation, "Aurora Green" Corps Helps Build South Mountain Wind Power of Caiyun

November 30, 2022

Recently,Yunnan provincial key project,The first Wind Turbine of Fuyuan West Wind Power Project is connected to the grid for power generation,It marks the successful operation of the largest single unit capacity Wind Turbine in mountain wind power in China.。Fuyuan West Wind Power Project is under construction,“Aurora Green”The legion is the pioneer.,South of the clouds.,Top of the mountains,A beautiful picture of the harmonious coexistence of Wind Turbines and the natural environment has been constructed.。

Fuyuan West Wind Farm is located in the mountains of Fuyuan County, Qujing City.,The total installed capacity of the project is 800,000 kilowatts.,Design and installation 135 fans,It is divided into three phases.。This time, the second phase of Maotianshui area was put into operation.,Goldwind's new generation of medium-speed permanent magnet series products,Wheel hub height 110m,Impeller diameter 191 m,Maximum lifting capacity 150 tons。It is the largest single unit capacity of mountain wind power in China at present.、The tower has the highest height、The leaves are the longest、Unit with the largest lifting capacity。

The project has successfully completed the hoisting of the first wind turbine since August 3 this year.,At present, the hoisting of 42 wind turbines has been completed.,It is planned to complete the hoisting of all the remaining wind turbines by the end of the year.,Realize grid-connected full operation。From the beginning of the first lifting of the project in early August,By September 22, the largest wind turbine in the second phase of the project was hoisted.,By mid-November, grid-connected power generation will be realized.。Along the way,There are scenery and challenges.。

 

Tangshan Shuaixin Construction Engineering Co., Ltd.、Maanshan Jiehao Machinery Equipment Co., Ltd.、Zhejiang Elephant Hoisting Transportation Co., Ltd.、Shanghai Suide Machinery Engineering Co., Ltd. and other enterprises have joined hands with Zoomlion Heavy Lifting Equipment to complete one project node after another.。Cangshan is like the sea,Towering on the top of the mountain“Big windmill”,A Beautiful Picture of Natural Harmony。

 

South of the clouds,Where the clouds rise,Wipe it“Aurora Green”It echoes with the green mountains and waters。There are veteran players in Zoomlion equipment involved in the project construction.ZCC11800,Completed the hoisting of the largest wind turbine unit in the second phase of the project;Hoist the kaleidoscopeZCC9800W,It's wind power、Evergreen Tree in Petrochemical Hoisting,It has created various types of wind power hoisting records.;Star product of all-terrain craneZAT18000H,Take 21 yearsTOP50 Golden Finger Awards,It is known as the peak of construction machinery products.;AlsoZCC13000、AndZCC3200VElectric control version and other types of equipment,All in the Fuyuan West Wind Power Project,Showing his majestic posture.。

 

The customer and the project team chose to use Zoomlion cranes.,It is the trust and affirmation of Zoomlion's lifting equipment.。And Zoomlion Crane will certainly live up to expectations.,Give back the trust of customers with precise and safe hoisting operations.。

 

The subsequent hoisting tasks are still proceeding in an orderly manner.,Want to complete the hoisting of all wind turbines by the end of the year,It also requires the concerted efforts of all staff and machinery.,Work together。

 

It is reported that,After the project is completed and put into production,Estimated annual on-grid electricity quantity 19.600 million kilowatt hours,About 64% of standard coal can be saved every year.10,000 tons,Reduce carbon dioxide emissions by about 173 per year.20,000 tons、Sulfur dioxide is about 1171.8 tons。Future,Zoomlion will adhere to scientific and technological innovation、Continue to explore,Contribute to the construction of green new energy in the motherland。

Featured

more

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China