Height 166m, diameter 200m! XCMG XGC 15000A completes the first lifting of the "largest mixed tower" wind turbine

October 09, 2022

Recently,In Xiangyang, Hubei,Xiangbei Wind and Storage Integrated Wind FarmFirst large height、Large MW mixed tower Wind TurbineGroupHoisting completed by Anhui Jinfu Company,The main construction equipment is XCMG 1000-ton Crawler Crane.——XGC15000A

5 of this hoistingMWUnit length: 97m,Maximum diameter up to200 meters,Height of hub center up to166 meters,The previous domestic record was diameter.191 metersAnd height160 meters

Scene,Owner experts said:“This is the absolute first mixed tower wind power in China.!Extra Long Rotating Diameter,It will bring more windward area.,The advantage of power generation efficiency is very obvious。”

It is understood that,Impeller diameter 200m,Its swept area is near.32000 square meters,Equivalent to 4.5 standard football fields。And 5MWFanIt can generate 10 million kilowatt-hours of electricity annually.,It is equivalent to saving 4000 tons of standard coal per year.,Reduce carbon dioxide emissions by about 8000 tons,Operate to generate electricity for one year,5 can be satisfied,Electricity demand for 1,000 households。

Fan height、For every 1 meter increase in size,The overall structure will bear more weight.200 meters in diameter,166m height hub,After all the equipment is in place,The tower has to withstand up to 2200 tons of tension.。Installation、During hoisting,Lifting equipment and operations teams are required to meet the highest industry standards,Ensure that subsequent power generation is foolproof。

Now,Over 160 meters in height“Mixed Tower”Is becoming the mainstream of the market。XGC15000AMaximum allowable height of 170 m,Hoist a large unit weighing 181 tons。

Prefabricated parts at all levels of the mixed tower,Or a steel tower,XGC15000AThe operation can be efficiently completed within the rated wind speed.,It is bound to become the leading model in the field of wind power hoisting in the future.,Continuously create value for customers。

After completion of first lifting,The 20 Wind Turbines in the first phase of the project are scheduled to be connected to the grid in December this year.。In the face of a tight schedule,At present, Anhui Jinfu has assembled many sets.XGC11000AAndXGC110ACrawler Crane mobilization,They will cooperate with the kiloton class to carry out multiple working faces.,Make every effort to ensure the smooth completion of the project。

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China