Shijiazhuang to ChengdeA new channel for expressway will be added.Look at it in detail↓↓↓
The opening time has been set.
The golden autumn season,Chengde is located in the expressway of the Capital Area Ring Line in Chengde.(Li Jiaying)To Pinggu(Boundary between Hebei and Beijing)The construction site of Duan Project is very busy.。It is reported that,ThisThe project will be completed in September 2024.Vehicle,This will become the second high-speed passage from Chengde to Beijing.,It is also the most convenient high-speed passage between Shijiazhuang and Chengde.。
Passing through these places in Hebei
The project started in Changshen expressway.(G25)Chengde Lijiaying Interchange,Through Yingshouyingzi mining area、Xinglong County,Stop at the boundary between Hebei and Beijing。The main line is about 59 kilometers long.,Adopt the standard construction of two-way six-lane expressway,Design speed 80 km/Hour,2 service areas are set along the whole line.、Parking area 1、2 maintenance work areas、3 tunnel management stations、Monitoring communication sub-center 1,4 connecting lines。The ratio of bridge to tunnel of the whole line is about 68%,It is the most difficult highway construction project in Chengde City.。The construction period is 3 years and 6 months.。
Progress
By the end of August this year,Subgrade works of the whole line completed accumulatively 61%,Bridge works completed accumulatively 27%,Tunnel works completed accumulatively 35%;Completed annual investment of 3.3 billion yuan,Accumulated investment completed 64.2 billion yuan,Accounting for 43% of the total project investment.9%。The whole line of the project carries out photovoltaic power generation.、Green ecological cave door、Research on Technical Innovation of Material Reuse in Reconstruction and Expansion Project,Strive to build a green and low-carbon expressway.。
Faster and more convenient
All the time,Drive from Shijiazhuang to Chengde,It needs to pass the Beijing-Hong Kong-Macao Expressway.(Or Beijing-Kunming Expressway)Turn to Beijing-Chengde Section of Daguang Expressway in Beijing,On holidays, the traffic flow in Beijing-Chengde section is large and prone to congestion.。After the Chengping Project is completed and opened to traffic,It will become an important part of the capital's outer ring.,It is the second high-speed passage between Chengde and Beijing.,It will also become Chengde and Tianjin.、The fastest time between Shijiazhuang、The most convenient high-speed access,Promote the development of tourism in Chengde。
December 11, 2024,Dongfeng Commercial Vehicle 2025 Annual Partner Conference Held in Chengdu。Based on the final season of 2024,Dongfeng Commercial Vehicle joins hands with more than 600 dealers nationwide、There are more than 1000 representatives of mor
December eleventh,With“WE ARE ONE——A family、One heart、Work together、It's going to work”The 2025 Global Supply Chain Strategic Partnership Conference of China Heavy Truck Group was held in Shandong International Convention a
The other day,Final judgment of the People's Court of Changsha County, Hunan Province,It was found that Anbaituo Trading Co., Ltd. had caused damage to the commercial reputation of Sunward Intelligence.,Its behavior constitutes unfair competition.
December 2,Beijing Party Branch of International Corporation and Construction Machinery Party Branch of China Construction Machinery Corporation、The General Party Branch of China has launched“Forging New Productive Forces and Promoting New Indust
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China