Products Center
More Products

Over trillion projects will start in the fourth quarter! The latest progress of the railway planned to start construction in 2022-2023

September 21, 2022

August 31, 2022,State Railway Group Holds Teleconference on Railway Construction。All construction units are required to follow the principle of opening as much as possible.,Take unconventional measures,Strive for 16+Four new projects should start construction as soon as possible.,To make due contributions to stabilizing the economic market。

Since August,“Fourteen five”Significant progress has been made in the preliminary work of planning major railway projects.。At present,Unapproved feasibility study projects are speeding up the approval of feasibility study.,The preliminary design and construction drawings of the projects that have been approved for feasibility study have been approved successively.,A large number of countries“Eight vertical and eight horizontal”High-speed railway channel“Broken road”The project has entered the bidding stage one after another.,Three、The fourth quarter will achieve the goal of full construction.。

These include the North Riverside high-speed railway of the high-speed railway corridor along the Yangtze River.、Chongqing-Wanzhou high-speed railway、Chengdu-Dawan high-speed railway;Xiongxin high-speed railway of Beijing-Kunming high-speed railway Corridor.、Xi'an-Chongqing high-speed railway;Commercial high-speed railway for the Beijing-Hong Kong high-speed railway Corridor.、Changjiu high-speed railway;Tianjin-Weifang high-speed railway for the Second Passage of Beijing-Shanghai high-speed railway;、Weisu high-speed railway;The high-speed railway of Tongyong in the Coastal high-speed railway Passage;、Shenjiang Railway;Lan(West)Xicheng Railway of Guangtong Road, etc.。

The latest progress of each project:

1、Xiongan-Shangqiu Section of Beijing-Hong Kong High-speed Railway(Xiongshang high-speed railway)The whole line(Including agent construction section)Construction tender announcements have been issued.,The whole line will be started in October.;

2、Shanxi Section of Xiongan-Xinzhou High-speed Railway、Hebei section(Excluding agent construction section)Construction tender announcement has been issued,The whole line will be started in October.;

3、High-speed railway along the Yangtze River from Shanghai to Nanjing to Hefei, Anhui、Jiangsu、Tender announcements for construction of Shanghai section have been issued.,The whole line will be started in October.;

4、Chengdu-Yingshan Section of Chengdu-Dazhou-Wanzhou high-speed railway Line、Tender announcements for construction of Yingshan to Wanzhou sections have been issued.,The whole line will be started in October.;

5、Preliminary design of Xining – Chengdu Railway has been approved,Qinghai、Gansu Section Construction Tender Announcement Has Been Issued,Sichuan section to be tendered,The whole line will be started within the year.;

6、The EIA report of Ankang-Chongqing section of Western Chongqing high-speed railway has been approved.,The preliminary design appraisal has been reviewed and will be approved soon,Construction drawings to be reviewed,Bidding for construction in the fourth quarter;

7、The tender announcement for the construction of Chongqing-Wanzhou high-speed railway has been issued.,The whole line will be started in October.;

8、The feasibility study of the Hefei-Wuhan section of the Shanghai-Chongqing-Chengdu high-speed railway has been submitted to the State Railway Group for approval.,Preliminary design to be reviewed,Control projects are expected to start in the year;

9、EIA Report of high-speed railway from Tianjin to Weifang Has Been Approved,Preliminary design has been approved,Tender is about to be invited;Tianjin-Weifang high-speed railway Jinan Liaison Line(Jibin high-speed railway)Construction tender announcement has been issued,The whole line will be started in October.;

10、The preliminary design of Ruijin-Meizhou Railway has been approved,Tender announcement for construction of Guangdong section has been issued,The whole line will be started within the year.;

11、Preliminary design of Taizicheng-Xilinhot Railway has been approved,Bidding for construction is imminent;

12、The feasibility study and preliminary design of Xi'an-Tongchuan Section of West Extension high-speed railway have been approved.,Construction will start within the year;

13、The preliminary design of Tongsu-Jiayong high-speed railway has been reviewed.,We will strive to start construction within the year.;

14、Yanyi high-speed railway Land Pre-examination Approved by the Ministry of Natural Resources,The second EIA has been publicized.,We will strive to start construction within the year.;

15、Preliminary Design of Nanjing Section of Ninghuai high-speed railway Has Been Approved,The whole line is about to start construction.;

16、Ningbo-Zhoushan RailwayPPPTender notice has been issued,Construction will start at the end of the year;

17、The feasibility study of the Yichang-Fuling section of the Shanghai-Chongqing-Chengdu high-speed railway along the Yangtze River will be reviewed soon,Strive to approve the feasibility study within the year;

18、The feasibility study of Chang-Gan high-speed railway has been submitted to the National Development and Reform Commission for approval.,Preliminary design reviewed;

19、The feasibility study of Shaoyong high-speed railway has been submitted to the State Railway Group for approval.;

20、The feasibility study of Zhangzhou-Shantou high-speed railway has been reported to the National Development and Reform Commission.,Feasibility study evaluation will be carried out soon,Preliminary design to be reviewed;

21、The feasibility study of Weifang-Suqian high-speed railway has been submitted to the State Railway Group for approval.,Preliminary design to be reviewed;

22、Harbin-Tieli Railway Construction Tender Announcement Issued,Construction of the whole line will start in November.,The construction period is 4 years;

23、The review meeting on feasibility study, appraisal and repair of Mianyang-Suining Railway has been held,The feasibility study is expected to be approved within the year.,The early stage will be started;

24、Fuyang to Mengcheng to Suzhou(Huaibei)Some sections of the railway have been tendered for construction,The whole line is about to start construction.,Duration 3.5 years;

25、Tender Announcement for Construction of Shenzhen-Jiangmen Railway Has Been Issued,The whole line will be started in October.,Duration 5.5 years;

26、Zhuhai-Zhaoqing high-speed railway Zhuhai-Jiangmen Section、The preliminary design of Gaoming-Zhaoqing East Section has been approved.,The whole line will be started within the year.;

27、The EIA report of the Pearl River Delta hub airport to the provincial boundary section of the Nanshen high-speed railway has been publicized.,The feasibility study will be approved.;

28、The feasibility study of Quzhou-Songyang Section of Quzhou-Lishui Railway has been approved;

29、Nanshen high-speed railway from Yulin to Cenxi(Boundary between Guangxi and Guangdong provinces)Section has been tendered for construction,Duration 3.5 years;

30、The section from Foshan Station to Guangzhou North Station of Guangzhou-Foshan Ring Line has been tendered for construction.,The construction period is 5 years;

31、The environmental impact assessment report of Tianfu-Chaoyang Lake section of Sichuan-Tibet Railway introduced into Chengdu hub has been approved.,Preliminary design will be approved soon;

32、The preliminary design of Guiyang-Guangzhou high-speed railway upgrading project will be approved soon,Construction will start within the year;

33、Preliminary design of Huangtong-Baise Railway has been previewed,The preliminary design of station building has been reviewed;

34、The adjustment feasibility study of Pingliang-Qingyang Railway has been reviewed.,We will strive to start construction within the year.;

35、The Feasibility Study Report of the Additional Second Line Project of Jinghe-Alashankou Section of Lanzhou-Xinjiang Railway has been approved,Preliminary design reviewed;

36、Wenshan-Mengzi Railway EIA Report Has Been Publicized,We will strive to start construction within the year.;

37、Feasibility Study of Kunming-Yuxi Railway Electrification Expansion and Reconstruction Project Reviewed;

38、Add a new item:Lop Nur to Ruoqiang Railway,The feasibility study has been reviewed,Strive to start construction within the year。

2022-List of Preliminary Progress of Railway Planned to be Commenced in 2023▼

Note:Red font is the content of this update。

 

 

Explain:Due to the long period of preliminary work of railway construction projects,,There are many unpredictable factors.,Whether the project in the table can be started on schedule is uncertain.,For information only,It will be updated from time to time.。

Source:Railway construction planning

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China