Jungheinrich expands automated tank store built by valve technologists in 2002,Added channel
Performance improvement:Bin library performance more than doubled by replanning
Connection of new systems and integration of existing facilities during operation
In the process of expansion:For more than 50 years,GSR VentiltechnikIt has been the development of standard and special valves for solenoid valves and pressure control.、A synonym for production and global sales experts。Its automated warehouse is located atVlotho,Location of the company's headquartersNorth Rhine-Westphalia,In order to significantly increase warehouse capacity,The valve technology company is now expanding its automated bin warehouse, which Jungheinrich helped build in 2002.。

For this purpose,Jungheinrich added a second roadway to the expanded automated bin store。Yonghengli Project ManagerChristian HopfExplain that:
“
The success of this project is of special significance to us.,Because the first automated bin warehouse solution created in 2002 also came from Jungheinrich.,This means that GSR VentiltechnikHave been our automation customer for almost 20 years,We are now able to successfully gain customer recognition again。
”
In particular,The second laneway delivered by Jungheinrich includes a steel rack structure.,As a reprogrammed 26.5 meters long、4.Part of a warehouse 2 metres wide and 8 metres high。The solution provided by Jungheinrich includes a delivery system.,Can be controlled from four inbound and order picking stations,Plus Stacker for new laneway。The Stacker of the original roadway has also been updated.。The solution also reserves space for the later installation of four workstations.。New Warehouse Management System (WMS) The control technology of the form also comes from the eternal force.。
After upgrade,Due to the addition of 4,740 storage locations and double deep shelves,Small Parts WarehouseGSR VentiltechnikThe flow of 160 containers per hour can be realized.。“A new laneway with Stacker has been added,And a Stacker which updates the original roadway.——That's why the facility's performance has more than doubled.,”HopfSummed upGSR VentiltechnikThe performance of has been significantly improved.。
VlothoThe new roadway is directly adjacent to the existing facility.,So it's very challenging to connect.,Pecially during operation。For this reason,The conveying system is specially constructed,So that it can be connected to an existing warehouse through an opening in the wall。The previous facility was closed and integrated only after the new channel began operation.。During this construction process,,Existing pick point is disabled。
GSR Ventiltechnik The technical director ofMichael BeerSay:
“
The transition from a small parts warehouse in 2002 to the new system went smoothly.,20 years ago and now.,We are committed to partnership and constructive cooperation with Jungheinrich.,Very satisfied as always.。
On December 12th, Asian Construction Equipment Group Co., Ltd. (abbreviated as ACE Group) Xuchang Production Base hosted a delegation of senior clients from The Republic of Tajikistan for an in-depth facility inspection. Guided by the warm winter sun, th
Despite the biting cold of early January, the spirit of international cooperation remained warm and vibrant. On January 5, 2026, three clients from Cameroon traveled thousands of miles to Henan, China, arriving with high expectations for a visit to Asian
Copyright Notice 2002-2026 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China