On February 7, the Changsha Development and Reform Commission issued a notice on issuing a major project investment plan for 2020 in Changsha.
In 2020, there will be 1,320 major projects in the city (including bundling projects, of which 716 are continuing construction projects and 604 are new construction projects). The total project investment is expected to be 1,624.5 billion yuan, and the estimated investment in 2020 is 359.2 billion yuan.
/> p>
Changsha City 2020 Government Investment Major Project Investment Plan
Changyichang Railway Project
The Changyi-Changzhou Railway starts from Changde Station in Changde City, passes Hanshou, Taojiang, Yiyang, Ningxiang to Changsha City, and introduces the Changsha-Zhutan Intercity Railway Changsha West Station with 5 stations. The total length of the project is 162.79 kilometers (including 5.97 kilometers of tie lines), of which the Changsha section is about 35.8 kilometers
Main construction content in 2020: completion of demolition and construction, construction started
▲ Bored pile construction site
Changyi High Speed Expansion Project
It passes through Wangcheng District, Ningxiang City, and Heshan District of Yiyang City, with a total length of 50.28 kilometers, adopts the standard of a two-way six-lane highway, and has a designed speed of 120 kilometers per hour. The Changsha section is 31.78 kilometers long, with 5 interchanges and 1 service area.
Main construction content in 2020: basically completed construction.
Changsha Huanghua Airport Reconstruction and Expansion
The third runway and the corresponding taxiway will be built on the east side of the second runway, the new T3 terminal building, and auxiliary facilities such as maintenance, freight, aviation, food and power supply.
The main construction content in 2020: accelerate the advance work and strive to start construction as soon as possible.
Rail Transit Line 3 Phase I Project
It starts at Shantang Station and ends at Guangsheng Station. The total length of the line is about 36.47 kilometers. There are 25 stations on the whole line.
Initial operation in July 2020
Rail Transit Line 5 Phase I Project
Starting at Shuiduhe Station and ending at Maozhutang Station, the line is approximately 22.50 kilometers long and has 18 stations on the entire line.
The initial operation will be realized in July 2020.
Rail Transit Line 6 Project
It starts at Wutong Road Station and ends at the West Airport Station Station. The total length of the line is about 48.11 kilometers. There are 34 stations on the entire line.
In 2020, most of the main station projects and section projects will be completed.
Changzhutan Intercity Rail Transit West Ring Line Phase I Project (All Lines)
It starts at Shantang Station, the terminal of Phase 1 of Metro Line 3, runs south along Tanzhou Avenue, and ends at Xiangtan North Station of Shanghai-Kunming High Speed Rail. The total length is 18 kilometers, of which 10.6 kilometers are in Changsha section and 7.4 kilometers in Xiangtan section.
Part of the main structure and interval construction in 2020.
City Rail Transit Second Control Center
The high-speed rail exhibition and new city area of Duhua Road and Lituo Road in the northwest block of land, an area of 8021.75 square meters, including the city's rail transit network and command center and other functions.
Earth and stone and foundation pit support will be completed by 2020.
Xiangya Road Crossing River Passage Project
It starts from Yuehua Road in the west and connects to Furong Middle Road in the east. It is about 4.18 kilometers long and includes two parts, the tunnel and the ground road. The tunnel is positioned as the city's main road, of which the cross section of the river is a two-way six-lane road, after the ramp is divided into a two-way four-lane road, and the ramp is a one-way single-lane road.
In 2020, the construction of the Hexi starting well and its supporting facilities will be completed, the underground shield assembly will be completed, and the Hedong receiving well will be basically completed.
Municipal supporting projects around South Bus Station Comprehensive Transportation Hub
It mainly includes Shaoshan Road (Times Sunshine Avenue-Gaosheng Road) rapid transformation and Xianfeng Road connecting South Bus Terminal Comprehensive Ramp Bridge. Construction of Xianfeng Road Ramp Bridge project started in advance
In 2020, the north-south ramp bridge of Xianfeng Road and its auxiliary projects will be completed and put into use.
Furong Avenue (Changsha Section) Rapid Reconstruction Project
The first phase of the project is currently implemented: from the north of Pitang Road to the junction of Changtan to the south, with a total length of about 12.8 kilometers, of which the urban section (Phitang Road-Shanghai-Kunming Railway) is about 8.5 kilometers in length. 60 meters; the section of the city (Shanghai-Kunming Railway-Changtan boundary) is about 4.3 kilometers long, the standard of a first-grade highway, and the implementation conditions of urban arterial roads are reserved. The current road width is 42-60 meters
The main line of the first phase of the project will be opened to traffic in December 2020.
Dongzhu Intercity Highway (Changsha Section) Reconstruction and Expansion Project
The starting point is at the intersection of Wanjiali Road and Environmental Protection Avenue. It is about 16.2 kilometers long, including 3.7 kilometers of environmental protection avenue section, and 12.5 kilometers of suburban highway section. It adopts the first-grade highway standard (taking into account the functions of urban roads) and has two lanes and six lanes. Main construction contents: 6 new bridges, 3 wide bridges, and 8 separated three-dimensional intersections in suburban highway sections
Construction will be completed by 2020.
Changsha Port Xianing Port Phase III Project
Construction of 6 new berth hydraulic structures, dredging of harbor basins and dredging of foundation trenches, earth and stone works for ground and track beams, land formation, production and auxiliary buildings of 17,706 square meters, power supply lighting, water supply and drainage, fire protection, environmental protection, Greening, soil and water conservation engineering, loading and unloading equipment, etc.
The main civil engineering construction in the southern area will be completed by 2020
High-speed Rail Convention and Exhibition New City Urban Village Reconstruction Project (Phase 1)
Reconstruction of urban villages in the east to east fourth lines, south to Yujin Road, west to Xiangrong West Road, and north to Laogong Road.
Partial demolition will be completed in 2020.
Medical Section of the No.4 Hospital Binshui New City Campus Construction Project (Phase I)
Newly constructed 6 individual buildings including outpatient and emergency medical technology building, inpatient building, research and teaching office building, and duty apartment building, with a building area of 153,000 square meters, and 900 beds.
Construction will be completed by 2020.
& nbsp; High-speed rail new city Mopanzhou construction project
It covers an area of about 175 mu and is located in the middle of Liuyang River from Labor Road to Xiangzhang Road. It mainly constructs ecological restoration projects.
Construction will be completed by 2020.
High-speed Rail West Station Municipal Comprehensive Supporting Project (Phase 1) Project (Project in PPP Package)
1. High-speed Rail West Station Set-up and Transportation Road Network Project
1.1. Zhanqian North Road (Jinling Road-Maqiaohe Road, 2200 meters in total)
1.2. Zhanqian South Road (Jinling Road-Maqiaohe Road, 2200 meters in total)
1.3. 240 meters in Guoliang Road (Zhanqian North Road-Zhanqian South Road) Railway Red Line
1.4. Jinling Road (Zhanqian South Road-Zhanqian North Road, a total of 390 meters)
1.5. Zhanqian West Road (Zhanqian South Road-Zhanqian North Road, a total of 420 meters)
1.6. Jinshan Road (Zhanqian South Road-Zhanqian North Road, 360 meters in total)
1.7. Zhanqian East Road (Zhanqian South Road-Zhanqian North Road, a total of 420 meters)
1.8. East Elevated Ramp (East Drop-off Platform-Maqiaohe Road, total 3500 meters)
2. District municipal supporting projects
Complete the design work of the land acquisition and demolition section and the road construction of the North Road before the start of construction; carry out some preliminary work.
& nbsp; Changsha High-speed Rail West Station Industry New City Government Supporting Project
1. High-speed Rail West Station Set-up and Transportation Road Network Project
1.1. West elevated ramp (West Drop-off Platform-Huangqiao Avenue, about 3500 meters)
1.2. Jinhe Road (Zhanqian South Road-Zhanqian North Road, a total of 385 meters)
1.3. Guo Liang Road (Zhanqian North Road-South Zhanqian Road) outside the railway red line, 210 meters in total
2. District municipal supporting projects
Complete part of the design work for the land acquisition and demolition section; carry out some preliminary work.
Changwang Road West Extension (West Second Ring Road-Golden Avenue)
It starts from the West Second Ring Road in the east and reaches the Golden Avenue in the west, with a total length of 5.2 kilometers and a road width of 46 meters.
In 2020, the Wangcheng section will be completed, and the Yuelu section will complete 70% of the subgrade earthwork.
Lujing Road South Extension Project (South to Hanpu Avenue)
It is about 3.9 kilometers long, including 2.3 kilometers of tunnel works, 1.6 kilometers of road works, urban expressways, and two-way six-lane roads.
In 2020, the main construction of the tunnel other than the pavement will be completed, and the main construction of the road will be completed.
The second section of the rapid reconstruction project of Tanzhou Avenue (the optimization project of the roundabout highway entrance)
It is a section of the rapid reconstruction project of Tanzhou Avenue. The north side is connected to Xiangfu Road (Hexi section) in the north of Liantang Road and the viaduct is connected to Liantang Road. The road is laid to the south to Lianping Avenue. 2.28 kilometers, the city's main road (Expressway).
By 2020, 80% of the lower structure of the bridge and 20% of the upper structure will be completed, and the auxiliary road foundation except for the impact of demolition will be completed.
Dawangshan Tourism Infrastructure Project
Construction of the Changsha Dawangshan Tourist Resort air rail transit sightseeing system with a line length of about 10 kilometers (Shantang Tourist Distribution Center-Guanyin Port Tourist Distribution Center), including the relocation of comprehensive pipelines such as electricity, telecommunications, and gas, and corresponding traffic diversion projects
In 2020, the foundation works in accordance with the soil regulations within the land area will be completed.
& nbsp; Yuelu Mountain Scenic West Gate
Including the west gate, parking lot, roads, bridges and other landscapes at the east entrance of Taohualing Scenic Area, bridges, landscapes, etc., the land area is about 138 acres.
The main construction of the underground parking lot has been basically completed, the main construction of the tourist service center has been basically completed, and the main construction of the bridge project has been basically completed.
& nbsp; Meipu Contact Line
The total length is about 4 kilometers (including a tunnel section of about 1.3 kilometers), including roads, tunnels, bridges, drainage, transportation, lighting and landscaping projects.
In 2020, the subgrade of the road section will be completed in the northern section, and the construction of the tunnel exit of the southern section will begin in the southern section.
Summer Cuckoo Road Tunnel
It includes 680 meters of connecting roads on both sides, of which the tunnel section is 280 meters long. The two-way eight-lane design in the tunnel.
Tunnel construction will be completed in 2020, and tunneling will begin.
Wanjiali Road Rapidly Renovates the North Extension Line
Viaduct section: The rapid extension of Wanjiali Road to the north extension line starts at Fuyuan Road and ends at Yonglong Road. The viaduct is 4.03 kilometers in length and has two lanes of 6 lanes. There are two ways to excavate the power tunnel: shield section and open cut section. The shield section is divided into two sections: the total length of the section from the Teli Road to the Ring Expressway Interchange is about 7.6 kilometers, of which 5.1 kilometers is the shield section. The shield section has a circular shape with an outer diameter of 4.1 meters and an inner diameter of 3.6 meters. The cut-out section is 2.5 kilometers, and the box section is 3.4 meters * 4.1 meters.
Part of the power tunnel and bridge pile foundations affected by Metro Line 5 will be completed by 2020.
Upgrading around Wuyi Commercial District
Comprehensively renovate the surrounding areas of the May Day business district, including facades, greening, and some municipal facilities.
Renovation of municipal facilities will be completed in 2020.
Changsha city government investment major project reserve catalog
Rail Transit Line 2 West Extension Phase II Project
Starting from Jinqiao Station and ending at Meixihu West Station, the line is approximately 14.72 kilometers long, with a total of 11 stations on the entire line.
Construction will begin in September 2020.
Rail Transit Line 1 North Extension Phase I Project
It starts at Caixia Road Station and ends at Kaifu District Government Station. The total length of the line is about 9.93 kilometers. There are 5 stations on the whole line.
Construction will begin in September 2020.
Malan Mountain Small Capacity Project
Improving commuting in the park and serving sightseeing tours are tentatively scheduled to start at the east gate of Martyrs Park and end at Zhongnan Bus World Station.
The preparatory work will begin in 2020, and the construction of social capital will begin after the identification of the social capital side.
Three halls and one hall across Liuyang River footbridge project
Located in the Xinhe Delta, the new pedestrian bridge across the Liuyang River from the third hall and the first hall to the north will improve the function of the urban slow-moving system.
Complete the preliminary work in 2020 and start construction.
Phase 1 of Line 7 (Yuntang Station-Apollo Plaza Station)
It runs from Yuntang Station in the south to Puyuan Road Station in the north and has a total length of 21.6 kilometers. There are 18 stations along the line (Yuntang Station-Apollo Plaza Station is 16.66 kilometers long, with 16 stations).
Feasibility review and approval will be completed in 2020.
Changyi Double Track to Xinglian Road Grand Passage Project
Bridge scheme: The whole line is 4,973 meters long, starting point: 200 meters west of Yinshan Road, ending point: 230 meters west of Beijing-Guangzhou Railway Bridge; the route passes through Xiangjiang One, Mushan District, Shanyucheng District, Qianlong Shijia District in turn. Total investment is about 3.23 billion yuan
Tunnel scheme: 1 section of the river-crossing tunnel (total length of the tunnel is 3,060 meters, of which the shield section is 1,971.2 meters), 2 underground interchanges, and 1 crossover bridge, 942.5 meters. The total cost is about 5.386 billion yuan.
After the study and determination of the bridge and tunnel schemes in 2020, the preparatory work will be improved, land acquisition and demolition will be carried out, and construction will begin.
North-South horizontal line
The total length of the North-South horizontal line is about 530 kilometers (including the Tongjing Xiangjiang River Bridge of the North Horizontal Line and the Muping Xiangjiang Bridge of the South Horizontal Line). The newly-built road is about 418 kilometers, of which the first-level highway is about 130 kilometers and the second-level highway is about 289 kilometers.
In 2020, in accordance with the principles of overall planning and design, and implementation by stages and stages, innovative investment and financing models will be created. After the funding source is confirmed, the Municipal Communications and Transportation Bureau will take the lead.
Nongjiaotang Area Rongcheng Town Project (tentative name)
Centering on the construction of Changzhutan Rongcheng Town, the construction of a full-age demonstration community, health center, rehabilitation hospital, genetic testing center, talent apartment, well-being hotel, international communication and exhibition center, health sports theme park, Rongcheng leisure square, Rongcheng Gymnasium, 5G network construction, parking lot, supporting roads, etc.
Project planning, planning, feasibility studies and other related work in 2020
High-speed Rail West Station Infrastructure and Public Service Supporting Projects
The infrastructure and public service supporting projects of the Municipal High-speed Rail West Station are important supporting functional projects of the Changsha Station of the Chongqing-Changsha and Xiamen High-speed Rail. The project is all underground space with a total area of 270,000 square meters. Among them, the urban three-dimensional transportation interchange space is about 170,000 square meters, the social Vehicle parking area is about 90,000 square meters, and the taxi transfer area is 10,000 square meters. The project construction period is 3.5 years.
The preliminary work will be completed in 2020, and construction will start in a timely manner.
Low-traffic rail transit line T2
Starting from Meixihu Art Center Station and finally Huizhi Road Station, the line is 10.2 kilometers long and has 13 stations.
Feasibility review and approval will be completed in 2020.
December 11, 2024,Dongfeng Commercial Vehicle 2025 Annual Partner Conference Held in Chengdu。Based on the final season of 2024,Dongfeng Commercial Vehicle joins hands with more than 600 dealers nationwide、There are more than 1000 representatives of mor
December eleventh,With“WE ARE ONE——A family、One heart、Work together、It's going to work”The 2025 Global Supply Chain Strategic Partnership Conference of China Heavy Truck Group was held in Shandong International Convention a
The other day,Final judgment of the People's Court of Changsha County, Hunan Province,It was found that Anbaituo Trading Co., Ltd. had caused damage to the commercial reputation of Sunward Intelligence.,Its behavior constitutes unfair competition.
December 2,Beijing Party Branch of International Corporation and Construction Machinery Party Branch of China Construction Machinery Corporation、The General Party Branch of China has launched“Forging New Productive Forces and Promoting New Indust
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China