Products Center
More Products

The 8 - bid project of yunnan - China water diversion chuxiong section contracted by kunming company of China railway no.8 engineering bureau is back to work

July 15, 2020

Recently, with the approval of the superior competent department, the construction of the 8-bid project in chuxiong section of yunnan-central diversion water contracted by kunming company of China railway no.8 engineering bureau has officially resumed work.

In strict accordance with the requirements and overall arrangements of the superior units and local governments for the resumption of construction and production of the project, the central yunnan diversion project has scientifically and rationally formulated the resumption plan, the resumption plan and the epidemic prevention work plan. The project department prepares epidemic prevention materials in advance, clarifies the responsibilities of prevention and control, effectively integrates human and material resources, positively coordinates local resources, reasonably adjusts the project implementation plan, and comprehensively arranges the preconditions for the resumption of the project. With the most stringent control measures and the strongest resources, the project department will strengthen the health monitoring, evaluation and management of the people in the outbreak site of new coronavirus infection, so as to realize the ldquo of coronavirus-infected pneumonia. Plugging, prevention and control ” To achieve & other; External blocking input and internal non-proliferation ” To lay the foundation for the successful resumption of the project.

At present, kunming company has called in 23 managers and 39 operators for the 8-bid project of chuxiong section of yunnan-central yunnan diversion. Project department in tunnel import Ming CAI home village groove excavation site conditions, strictly implement the closed management, complete with sufficient surgical masks, infrared thermometer, alcohol, 84 disinfection liquid such as epidemic prevention and control objects, and set up under observation room, every day in completes the daily morning and evening temperature detection at the same time, the regional disinfection operations division point, points of term of outbreak of project department of personnel management, every day to the worksite, team to evaluate epidemic prevention and control the overall situation, to increase contact with local health and epidemic prevention departments work, ensure that on the premise of paying special attention to the epidemic prevention and control, steadily push forward construction of the project.

It is reported that the dian-china water diversion project belongs to yunnan province. Four hundred; The construction project is required by the provincial party committee and the provincial government according to the "letter of yunnan yunnan-central diversion project construction administration on supporting the construction of project resumption “ convenient channel ” and ensuring the relevant elements". Yunnan-central water diversion project to play a model role in the participation of personnel must be posted as soon as possible to take the lead to resume work. Kunming company actively responded to the call, the official resumption of the yunnan-china water diversion project shows China railway China iron man “ Pathbreaker ” The spiritual essence and the fighting spirit of the charge line.

Featured

more

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China