Shenzhen version of "xiaotangshan" overnight construction, more than 60,000 square meters, new 1,000 beds

June 14, 2020

At 23:00 on February 2, a reporter visited the construction site of the second phase of shenzhen third people's hospital overnight. The construction team rushed to build the project overnight. It is estimated that the project will cover an area of more than 60,000 square meters and 1000 additional beds will be available upon completion, yate news reported.


It is worth mentioning that the above construction project is known as the shenzhen version. Xiaotangshan & throughout; .

The news office of the guangdong provincial government held a press conference on January 21 to confirm 14 confirmed cases of pneumonia caused by the new coronavirus in guangdong, and announced 30 designated hospitals in the province, of which only one is the third people's hospital in shenzhen, thepaper.cn reported.

According to the official website of shenzhen third people's hospital, the hospital is a tertiary first-class hospital specializing in infectious diseases. It is mainly responsible for the prevention and control of infectious diseases and major outbreaks in shenzhen and its surrounding cities of Hong Kong, Macao, zhuhai, dongguan and huizhou, as well as the comprehensive medical services for shenzhen residents.

According to & other; Throughout southern + &; According to a report on February 2, all confirmed and suspected cases of pneumonia infected by the new coronavirus in shenzhen were treated at the third people's hospital of shenzhen, the national center for clinical medicine of infectious diseases. On the evening of January 28, in order to free up appropriate isolation beds, the hospital started the new coronavirus nucleic acid test negative patients referred.

The above report shows that in the guangdong provincial government information office of the seventh news conference on the prevention and control of the epidemic response to the reporter's questions, in the face of the reporter put forward by the ldquo; How to deal with the challenges of epidemic prevention and control brought by the people returning to shenzhen after the festival and whether shenzhen has enough treatment capacity ” Wu yihuan, deputy mayor of shenzhen municipal people's government, deputy director of the municipal epidemic prevention and control headquarters, and luo lesuan, director of shenzhen health and fitness commission, mentioned in response that the construction of the second phase of shenzhen third people's hospital should be accelerated to add 1000 beds in a short time to meet the needs of treating and treating patients.

& other; According to the & lsquo; Better be prepared than unprepared. ", shenzhen third people's hospital transferred ordinary patients, freed up 1,100 beds to ensure treatment capacity, and accelerated the construction of the second phase of shenzhen third people's hospital. Throughout the &; Wu yihuan said.

According to data released by the shenzhen health and fitness commission, as of 24 o 'clock on February 2, shenzhen's New pneumonia ” The total number of cases has reached 226, the most in guangdong province.

Wuhan vulcan mountain hospital delivered

Eight days later, a 1,000-bed hospital was opened. It is a constant race against time. Battle & throughout; . Beijing daily client reporter on February 2, China construction of the third bureau learned that wuhan vulcan mountain hospital delivery. The vulcan mountain hospital, with a total floor area of 33,900 square meters, will officially receive pneumonia patients infected by the new coronavirus on Wednesday, as was built in xiaotangshan hospital in Beijing during the SARS outbreak in 2003.


Xinhua news agency reporter xiao yijiu photo vulcan mountain hospital data map

Before vulcan mountain hospital, the Chinese probably never cared so much about the construction of a hospital. Every day, tens of millions of people sit in front of screens big and small and volunteer to be part of it. Cloud the supervisor & throughout; For builders drum with shout.

Every minute counts! It's a race against time. Tug-of-war & throughout; The game.

On January 24, New Year's eve, hundreds of Excavators arrived at the site and began to level the land.

January 25, the first day of the New Year, vulcan mountain hospital officially started.

On January 26, the second day of the lunar New Year, the construction of impermeable layer was fully carried out, the underground pipe network trench was excavated, and the materials of container board room were successively entered.

On January 27, on the third day of the lunar New Year, site leveling, gravel and sand backfilling were completed, and the first batch of paneled container houses were hoisted and built.

January 28, the fourth day of the New Year, the steel structure of the first double-storey hospital ward began to take shape.

On January 29, the fifth day of the lunar New Year, more than 300 box-type housing frames were installed and mechanical and electrical pipelines were started simultaneously.

On January 30, the 6th day of the lunar New Year, the HDPE membrane laying was completed, and the equipment hoisting of the sewage treatment room was carried out simultaneously.

On January 31, the seventh day of the lunar New Year, the assembly of 90% of the containers has been completed, and the frame of the movable board room has been installed 3,000 square meters.

February 1, the eighth day of the lunar New Year, the full implementation of medical equipment installation.

February 2, New Year's day nine, vulcan mountain hospital project delivery.

During the peak period, more than 4,000 builders were on site, and nearly 1,000 large machinery and Vehicles were being built around the clock, demonstrating once again China's speed and power.

Some foreign netizens after watching the construction site video comments: “ Unbelievable builder. In Australia, it takes 25 years for the government to decide and another 20 years to build. Throughout the &;

Source: Beijing daily app

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China