Bauer announced the completion of the Monte Grande project, an ambitious water infrastructure initiative in the southwestern province of Barahona, Dominican Republic, led by the National Institute of Hydraulic Resources (INDRHI).
BAUER_Monte+Grande+Dam
In addition to controlling water levels in the Yaque del Sur River, the 55 m high dam will also be used for flood protection and hydropower generation. Other aspects include tourism and the use of dammed water for irrigation of agricultural land.
BAUER Fundaciones Dominicana S.R.L., a subsidiary of BAUER Spezialtiefbau GmbH, was commissioned to build a cut-off wall to seal the base of the dam.
Work began in May 2019 and was successfully completed in May 2020. In total, Bauer built around 26,000 m² of cut-off walls over a length of 1,350 m, up to an average depth of 23 m and a thickness of 800 mm below the base of the dam. Bauer Dominicana used a BAUER MC 96 work cycle crane with a BAUER BC 40 cutter, as well as a BAUER MAT Slurry Handling Systems BE 500 separation plant for the construction.
This project was the first time a trench cutter was used in the Dominican Republic, and was also the first time Bauer Dominicana has been part of a dam construction project.
A particularly challenging aspect was the extremely variable working height, which ranged from 152 my 197 m above sea level along the dam. "To cope with this height difference, 17 different working platforms were created from which the cut-off wall was built with a cutter", explained Bruno Luz, Project Manager of BAUER Fundaciones Dominicana S.R.L.
"We are very proud of our contribution to an infrastructure project that is so important for the region," says Bruno Luz in conclusion. "In addition to this, we were also able to gain experience in the construction of cutting walls with a cutter.
Previous: Sinoboom NA appoints sales director
On December 12th, Asian Construction Equipment Group Co., Ltd. (abbreviated as ACE Group) Xuchang Production Base hosted a delegation of senior clients from The Republic of Tajikistan for an in-depth facility inspection. Guided by the warm winter sun, th
Despite the biting cold of early January, the spirit of international cooperation remained warm and vibrant. On January 5, 2026, three clients from Cameroon traveled thousands of miles to Henan, China, arriving with high expectations for a visit to Asian
December 11, 2024,Dongfeng Commercial Vehicle 2025 Annual Partner Conference Held in Chengdu。Based on the final season of 2024,Dongfeng Commercial Vehicle joins hands with more than 600 dealers nationwide、There are more than 1000 representatives of mor
December eleventh,With“WE ARE ONE——A family、One heart、Work together、It's going to work”The 2025 Global Supply Chain Strategic Partnership Conference of China Heavy Truck Group was held in Shandong International Convention a
Copyright Notice 2002-2026 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China