July 07, 2016
As the originator of China’s kiloton crane, XCMG owns a brilliant record. Since their actual application in 2012, more than 20 kiloton cranes have worked in wind power projects in Fujian, Guangzhou, Yunnan, Inner Mongolia, Shanxi and other areas, lifting over 1600 sets of 2MW Wind Turbine. The strong lifting strength and perfect performance have won high praise from the construction side.
In the early hours of June 18, 2016, crane owner Mr. Liu with XCMG service team came to a large wind power project in Chifeng City, Inner Mongolia, where a large scale hoisting movie will be on stage.
The road is very clean after heavy rain two days ago, but in entering the construction site, the crane has to drive through a 4-meter-wide and 30-kilometer-long dirt road with more than 50 slopes of different degrees. The road is a tough task for ordinary Vehicles, not to mention the 19-meter-long and 90-ton-weight crane.
Under the guidance of XCMG service engineer, the driver soon feels the surging power of QAY800 when stepping on the accelerator. Rushing to the battlefield, the driver easily uses various electro hydraulic control steering modes like road mode, small turning, crab walking and successfully reaches the destination. "I feel a little bit too easy to drive this big guy," the driver joked.
Mr. Liu said when he accepted the task, he was a bit worried. The environment of the construction site is really bad. Despite the good quality of XCMG crane, it is very difficult to assemble such a monster in such a confined space. However, with the hard working and dedicated XCMG workers, he was fully relaxed.
In the strong wind, XCMG service team methodically installed the arm, chassis and leg. "The advanced self-assembly technique has saved us a lot of time. What’s more, it saves the cost of a set of auxiliary crane," Mr. Liu said with smile.
The self assembly process compares to a crane version of Transformers.
In the first hanging, the 84-meter-long main arm super lift working condition and 16-meter-long special wind arm of QAY800 firmly dock the 65-ton-weight head on the 85 meters-high tower base. The bolt contrapuntal, cable release and 40-meter-long leaves docking are successively completed.
In the following three days, the QAY800 has installed 2 sets of 2.0 MW Wind Turbine, during which with 800-ton-heavy load and super lifting device, it has climbed hills with slopes of nearly 40%. It is said that another 33 sets of Wind Turbine are waiting for installation on the site. There is no doubt that with the 800 tons super transitions ability and excellent lifting performance, the QAY800 will give excellent performance!
December 11, 2024,Dongfeng Commercial Vehicle 2025 Annual Partner Conference Held in Chengdu。Based on the final season of 2024,Dongfeng Commercial Vehicle joins hands with more than 600 dealers nationwide、There are more than 1000 representatives of mor
December eleventh,With“WE ARE ONE——A family、One heart、Work together、It's going to work”The 2025 Global Supply Chain Strategic Partnership Conference of China Heavy Truck Group was held in Shandong International Convention a
The other day,Final judgment of the People's Court of Changsha County, Hunan Province,It was found that Anbaituo Trading Co., Ltd. had caused damage to the commercial reputation of Sunward Intelligence.,Its behavior constitutes unfair competition.
December 2,Beijing Party Branch of International Corporation and Construction Machinery Party Branch of China Construction Machinery Corporation、The General Party Branch of China has launched“Forging New Productive Forces and Promoting New Indust
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China