July 19,Tarim 1.2 million tons undertaken by the Sixth Construction Company/The radiation chamber of the first cracking furnace of the second phase ethylene plant was successfully hoisted in place at one time in,The 800-ton Crawler Crane developed by Zoomlion undertakes the main lifting task in this hoisting.,Smooth realization of project construction 7·30 Milestone Level 1 Node,It marks that the second phase of Tarim ethylene plant has entered the installation stage.。
It is reported that,There are 7 cracking furnaces in the ethylene plant of Tarim Phase II Ethylene Project.,Including 2 gas furnaces and 5 liquid furnace,Each cracking furnace consists of two radiation chambers.。The cracking furnace is manufactured by modular prefabrication.、Construction mode of integral hoisting,And that manufacture and installation period is greatly shortened.。
The hoisting process has high requirements.、Difficult,Pecially for the site geology,The project department has formulated a special hoisting plan.。F1501BThe length of the radiation chamber is 33.83 meters、Width 4.06 meters,High 17.7 meters,The net weight is 193 tons,The actual hoisting weight is 219 tons.。In order to make the hoisting work go smoothly,,Zoomlion 800-ton Crawler Crane is used as the main crane on site.,320-ton and 120-ton Crawler Crane combined tail“Three-machine coordination”Hoisting method。
Ten a m:57,The hoisting work of the radiation chamber officially began.,Under the signal guidance of the current lifting command,01 pm:05 points,F1501BThe radiation chamber is firmly located on the foundation.。
The strong bear the burden,Zoomlion Crane will continue to contribute to the construction of Shenzhou.。
Heavy new products of Jingong New Energy Departure from Shanghai BMW Exhibition, Look forward to working with you“Horse”See you up there! More highlights,Invite you to experience in person Outdoor
To further enhance the service of financial assistance to enterprises,Promoting Inclusive Financial Services and High-quality Development of Private Economy,Recently,Zhang Meng, chairman of Liaoyuan Federation of Industry and Commerce, led represe
Four years away,The eyes of millions of people。 November twenty sixth-The 29th,bauma CHINA 2024 It will be held in Shanghai New International Expo Center.。Zoomlion Intelligent High Machine will be“New heights、New series、New technology&rd
Provide you with commercial concrete、Asphalt mixture、Professional knowledge and training information of dry-mixed mortar series mixing equipment and construction waste recycling equipment and solutions。 ,Duration 01:37
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China