China's Qinling Station in Antarctica,It is the fifth Antarctic research station in China.。It lasted 52 days,China's Antarctic Qinling Station Completed and Put into Operation with High Standards,Light up the new coordinates of the frozen continent.,Create a new benchmark for polar architecture。Engineer Liu's skill master Wei Subin,During China's 40th Antarctic Expedition,It is mainly responsible for the construction of Qinling Station and the maintenance of local construction machinery.。
During the construction of Qinling Railway Station,What are some memorable stories??What are the difficulties in the construction of Qinling Station??How does Liugong equipment perform in it??Let's take a look.。
Mention the South Pole,Many people think of glaciers as far as the eye can see,Penguin、 Whale ,But for Wei Subin,,Behind the Spectacle of the Polar World,It is a challenge to the limits of human body and engineering machinery.。
Polar day、A fierce wind、 Heavy snow 、Strong ultraviolet radiation……Enksburg Island in Antarctica has a harsh natural environment.,In such an environment,,Complete the walk、Ordinary movements such as standing are still very difficult.,In order to ensure the completion of the construction of Qinling Station on schedule, more than 100 members of the construction team,Strive to overcome the challenges of an extremely difficult environment,52 days to complete the construction of Qinling Station,Created a miracle。Wei Subin as a participant and witness,I have a deep feeling。
Guan Shan is difficult to cross——Fight for the world pole
This is not Wei Subin's first trip to Antarctica.,He had previously participated in the 39th Antarctic scientific expedition.,It is precisely because of the previous excellent performance.,He received an invitation to the 40th Antarctic expedition and passed the examination smoothly.。
November 2023,An advance team of 32 members, including Wei Subin, arrived at the construction site of Qinling Station ahead of schedule.,Carry out preparatory work。Unlike before,This time they're facing a glacier.,It should be used to complete the unloading of materials in a short time.、Equipment commissioning、Site leveling and construction of beach-grabbing wharf,To welcome the arrival of the main force.。
The first batch“Eat crabs”The people,Destined to face more difficulties.。Inclement weather combined with unfinished living quarters,And shortages of materials.,Wei Subin, who had worked and lived in Antarctica before, also called it hard.。At that time,Because the ice is too thick.,The merchant ship carrying supplies was delayed for two days.,He and his team turned the edible food upside down.,And burned the cabbage leaves.,Use a roll of paper.,Pass by“Smoking addiction”。
Fight against the wind and snow——From the South Pole“Qinling Mountains”
But the real battle,Only after the construction of Qinling Station began did it begin.。The area where Qinling Station is located is famous in Antarctica.“Tuyere”One of them,For safety reasons,In other places, as long as the wind force exceeds level 5, construction machinery can not carry out operations.,And here,Even though the wind has reached 8.、Level 9,The equipment is still working normally.。
Because the Antarctic is mostly based on rocks.,The texture is hard,In addition, Qinling Station adheres to the concept of green construction.,The stones used in the construction are all from the local rock after crushing.,This not only tests the performance of construction machinery.,It also increased Wei Subin's workload.。He adjusted the equipment according to the specific working conditions in Antarctica.,At the same time, the operators were carefully trained on the use of skills.,During the whole construction period,Engineer Liu's breaking hammer has not broken down once.,The durability of Liugong's equipment has also received unanimous praise from the team members.。
Construction in Antarctica is different from other regions.,The Antarctic continent usually has only a short summer from December to February.,This period is the best window period for construction operation.。To catch up,The players usually go out at half past seven in the morning.,The working time is about 14 hours a day.,Until the weather conditions are so bad that construction can no longer be carried out.,To pull a rope in a strong wind.,Grope back to the dormitory.。Traditional festivals in China——During the Spring Festival,They didn't stop working.,Instead, we will continue to work overtime to build the Qinling Station.。
Except for Excavators,Engineer Liu also has loaders、Aerial work platform、Skid Steer Loader、Application of Mining Wide-body Vehicle in Construction of Qinling Railway Station,The total number of equipment is 22.,It is the largest number of construction machinery brands participating in the construction of the station.。Wei Subin said,Whenever I see Liugong's equipment working neatly on the Antarctic land.,His heart is always full of pride and pride.。
The voyage has ended,Seek the infinite。This year marks the 40th anniversary of China's polar expedition.,For forty years,Generation after generation of Chinese expedition members bravely fought against the extreme cold.、Fight tenaciously,Constantly exploring the mysteries of the earth's polar regions。It has become a species used in polar scientific research in China.、Quantity(Table set)Most brands of construction machinery,Engineer Liu will also be solid and reliable.、Construction machinery and equipment with excellent performance continue to contribute to polar scientific research.。
Shanghai BMW show —— The grand meeting of the construction machinery industry Shanghai BMW show(bauma CHINA)The largest in Asia、The world's second largest construction machinery industry event。It brings t
November 14-The 15th,Party Secretary of Shaanxi Construction Machinery Co., Ltd.、Chairman Yang Hongjun,Chief Financial Officer Yang Juan and his delegation went to Hainan Pangyuan Machinery Engineering Co., Ltd. to investigate the const
Recently,The construction site of an open-pit iron ore mining project in Liaoning Province is a hot scene.,Count Taishan TuiSE800 mine excavators are on fire.,Work together to speed up the construction period,Press the acceleration key for the efficien
According to Gaogong Industrial Research Institute(GGII) Statistics ,In 2023, the overall sales volume of mining cards in China was about 30,000 units.,The sales volume of new energy mining cards is more than 1500.。With“Side mining、Edge repair&rd
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China