June 17, 2024
As a strategy to promote the development of Guangdong-Hong Kong-Macao Greater Bay Area
Critical infrastructure
Shenzhen-Shantou Railway ProjectConstruction
It has attracted much attention
Recently,Shenzhen-Shantou Railway Project
Construction site of Luohu North Station Section
XCMG Assembles Complete Set of Equipment to Attack
Inject strong kinetic energy into project construction
Shenzhen-Shantou Railway Project
It's the country“Eight horizontal and eight vertical”In the high-speed railway network
An important part of the coastal corridor
Guangdong-Hong Kong-Macao Greater Bay Area
An important carrier of eastward radiation
It is also a special cooperation zone between Shenzhen and Shantou.
“Five iron and five high”An important part of outreach transportation
Shenzhen-Shantou Railway is drawn from Xili Station of Shenzhen Railway Hub.,Via Shenzhen Luohu、Ping Shan、Huiyang, Huizhou、Huidong,Access to Shenzhen-Shantou Station of Guangzhou-Shantou High-speed Railway,Total length of main line 125.486 kilometers,39 bridges,18 tunnels。
The design speed of Shenzhen-Shantou Railway is 350 Kilometer/Hour,It is expected to be completed,It only takes 30 minutes from Shenzhen-Shantou Special Cooperation Zone to the central area of Shenzhen.,The Shenzhen-Shantou Special Cooperation Zone will accelerate its integrated development with Shenzhen.、Integration into the Guangdong-Hong Kong-Macao Greater Bay Area is of great significance。
▲Layout Plan of Shenzhen-Shantou Railway Project
Shenzhen-Shantou Railway Project
SSSG—Construction Site of Lot 8 Luohu North Station Project
Several XCMG Rotary Drilling Rigs、Diaphragm wall Hydraulic Grab、
Assembly of complete sets of equipment such as double-wheel slot Milling Machine
Put all efforts into construction
The total length of the line is 126 kilometers.,Construction requires a maximum wall depth of 48mLeft and right,Average depth 45m,Average rock entry at 20-25m,The hardness of the rock formation is 60-110Mpa,The average weight of the reinforcement cage is 70t。
To ensure smooth construction,According to the geological characteristics,,8 sets of XCMG equipment have been put into operation,Cooperate with the sand layer、Construction of rock entry section。
Among,XugongXTCThe 120 double-wheel slot Milling Machine is outstanding in construction.,Its fully guided three generation heavy duty turret、Three generations of drive units and heavy-duty milling wheels increase the torque by 10 percent%。High quality、High efficiency、The characteristics of low cost have been well received by the project side.。
XCMG Rotary Drilling Rig relies on flexible power head mode switching.、Special hydraulic telescopic crawler chassis and large diameter slewing bearing,It ensures the stability and convenience of construction.。
Cross-sea Passage from Mawan、Deep and medium passage
Shenzhen-Shantou Railway Project
The figure of Xugong shuttled among them.
Every dig.、Each pouring
They are all interconnected in the Greater Bay Area.
Solid help
September twenty fifth,Wang Ping, External Director of China Fuma Machinery Group Co., Ltd.、Yang Jianhui、Lu yuanlin、Li Quan and his party went to Changlin Company for investigation。Party Secretary of China Fuma、Chairman Jing Xinbao,Member of China Fuma
This hybrid mining dump truck with a load of 300 tons was successfully offline.,It is not only an important mileston
Recently,Independently developed by SunwardSWSL0607HAElectric hydraulic scissor aerial work platform successfully rolled off the production line,Maximum operating height of this model 6.5m,Platform load 240kg,A new breakthrough has been achieved in the
Cool season in the golden autumn,The Chinese University of Hong Kong welcomed a feast of wisdom and enlightenment.。September twenty seventh,Chairman Shi Weibin was invited to visit the Chinese University of Hong Kong,For graduate and doctoral stud
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China