March twenty seventh,SANY 3600-ton Crawler CraneSCC36000A,Complete the steel containment vessel of Unit 1 of Guangdong Lianjiang Nuclear Power Phase I Project(CV)The first ring of the cylinder was successfully hoisted in place.,Important engineering nodes of project realization。
Steel containment isCAPMain equipment of 1000 nuclear power unit,From the bottom head、Cylinder from the first ring to the third ring、Top sealing head consists of five module,It is the third safety barrier of the nuclear island reactor plant.。The weight of the first ring of the cylinder is 883 tons.,Gross shipping weight 945.3 tons,The total hoisting weight is about 1010 tons.。
Guangdong Thermal Power Special Company is responsible forCVTransportation of one ring of cylinder、Lifting task。
CVThe first ring of the cylinder is used as an annular cylinder module which is firstly positioned.,With large overall load、Features of high installation accuracy。The equipment is heavy、Easy to deform、The transportation center of gravity is high,And that Vehicle enter range is limited.,Modular Vehicle/ 'target='_blank' style='color:blue;'>Transport Vehicle assembly time is tight、The task is heavy。
March 26 5:20,CVThe first ring of the cylinder is transported from the workshop.,Pass bySPMTJacking、Fixed、Transportation and other processes,At 8:00 Transportation to the lifting parking point,Transport distance 930m,Via 2 right-angle bends,1 hour and 24 minutes。
March 27 14:13,CVFormal lifting of the first ring of the cylinder,SCC36000ASlowly lift it away from the Transport Vehicle,At 17:17 Successfully hoisted in place,After three hours and four minutes.。
This hoisting,The time for the crane to enter the hoisting site is short.,The super-lift counterweight is limited by ground pressure and needs to be increased successively before hoisting.,It is difficult to install,In addition,CVThe volume of the first ring of the cylinder is large, and the thickness of the lower opening cylinder wall is only 47.6 mm,It needs to be hoisted overCA20 top of the module,Precise placement on the bottom head,The overall operating radius is far,It is difficult to level the center of gravity。
Through the joint efforts of project personnel,Final,SCC36000AHigh-quality realization of one-time accurate positioning of No.1 nuclear island cylinder,The whole process is safe、Smooth、Orderly。
(Source of content :State Power Investment Corporation、CNNC 23、Guangdong Thermal Power Special Company)
December 11, 2024,Dongfeng Commercial Vehicle 2025 Annual Partner Conference Held in Chengdu。Based on the final season of 2024,Dongfeng Commercial Vehicle joins hands with more than 600 dealers nationwide、There are more than 1000 representatives of mor
December eleventh,With“WE ARE ONE——A family、One heart、Work together、It's going to work”The 2025 Global Supply Chain Strategic Partnership Conference of China Heavy Truck Group was held in Shandong International Convention a
The other day,Final judgment of the People's Court of Changsha County, Hunan Province,It was found that Anbaituo Trading Co., Ltd. had caused damage to the commercial reputation of Sunward Intelligence.,Its behavior constitutes unfair competition.
December 2,Beijing Party Branch of International Corporation and Construction Machinery Party Branch of China Construction Machinery Corporation、The General Party Branch of China has launched“Forging New Productive Forces and Promoting New Indust
Copyright Notice 2002-2025 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China