Chaoma Intercity Railway Comprehensively Promotes the Latest Progress of a Number of Railway Projects in Anhui

March 13, 2024

Fuyang Section of Fuhuai Intercity Railway Enters Girder Erection Construction;The Xuanji high-speed railway is scheduled to open in September this year.;Chaohu-Ma'anshan Intercity Railway Comprehensively Promotes Main Works……The other day,Da Wan News reporter learned from Anhui Railway Investment Co., Ltd.,A batch of railways under construction in Anhui Province ushered in new progress.,Co-construction for high quality“Yangtze River Delta on the track”Contribute。

Construction of girder erection begins in Fuyang section of Fuhuai Intercity Railway

The other day,In Wuming Town, Yingquan District, Fuyang City,Successful Erection of the First Box Girder of the 4th Bid Box Girder in Front of Fuhuai Railway Station,It marks that the Fuyang section of Fuhuai Railway has entered the stage of girder erection in an all-round way.,Speeding up the construction progress of the whole line of the project。

According to introduction,Fuhuai Intercity Railway is a national railway.《Medium and long term railway network planning》And《Integrated Development Plan for Higher Quality Transportation in the Yangtze River Delta Region》Key projects in China,It is an important part of the inter-city railway network in northern Anhui.。The railway starts from Fuyang West Railway Station of Shanghai-Hefei-Hangzhou Railway.,Through Lixin County, Bozhou City、Mengcheng County,It stops at Shuangduiji Station of Huai-Su-Bengbu Railway under construction.,It is a fast passenger passage from Fuyang to Huaibei.。

The main line of the railway is 143 kilometers long.,There are 4 stations on the whole line.,Simultaneous construction of Yingquan Station,Fuyang West Station and Shuangduiji Station are junction stations.,Mengcheng station、Lixin Station is an intermediate station.。The design speed is 350 kilometers per hour,The total investment is about 22.5 billion yuan.。At present,Land acquisition, demolition and roadbed are being promoted at the site.、Construction of main works such as bridges,It is planned to open to traffic in June 2026.。After the completion of the whole project,,From Fuyang to Suzhou、Huaibei will be shortened from about 2 hours to less than 1 hour.。

The Xuanji high-speed railway is scheduled to open in September this year.

Recently,Successful Erection of the First Catenary between Xuancheng and Ningguo South Section of Xuanji High-speed Railway,It marks that the high-speed railway has entered the construction stage of catenary network in an all-round way.。

Xuanji High-speed Railway is located in Xuancheng City, Anhui Province.,Xuanzhou District, Xuancheng City in the north,South to Jixi County,Total length 111.Six kilometers,A total of Xuancheng、Ning Guonan、3 stations in the north of Jixi,The design speed is 350 kilometers per hour,The total investment is about 15.6 billion yuan.。At present,The project is advancing track laying.、Construction of four electricity and station building works behind the station,It is planned to be completed and opened in September 2024。

Xuanji High-speed Railway is a high-speed railway corridor in Jiangsu, Anhui and Jiangxi.、An important part of the inter-city railway network in Wanjiang area,It is the backbone line of the Yangtze River Delta inter-city rail transit network.。After the project is completed and put into operation,The layout of regional road network will be further improved.,Shorten the space-time distance between Jiangsu, Anhui and Jiangxi,To develop tourism resources along the line,Promoting the Construction of International Cultural Tourism Demonstration Zone in Southern Anhui,Promoting the coordinated development of regional economy is of great significance.。After completion,From Wuhu, you can take the high-speed rail directly to Huangshan.,As soon as or at 75~Go directly to Huangshan within 90 minutes,Compared with the current 3 hours and 11 minutes.,The whole journey takes at least half the time.。

Chaoma Intercity Railway Comprehensively Promotes the Main Project

The other day,Completion of pouring of the largest pile cap of the main pier of the continuous rigid frame of Lot 4 of Chaozhou-Maoming Intercity Railway。The reporter learned,The main construction of the project has been more than half.,It is advancing in an all-round way.。

According to introduction,Chaoma Intercity Railway starts from Chaohu East Railway Station.,It runs eastward through Hanshan County、He County、Zhengpugang New Area、Dangtu County、Economic Development Zone、Rain Mountain area、After Huashan District,Introduction to Ma'anshan East Station,The main line is 61 kilometers long.,The design speed is 350 kilometers per hour。Chaohu East is located along the line.(Existing)、Hanshan、Zheng Pugang、Ma'anshan South、Ma'anshan East(Existing)5 stations in total。This year,Ma'anshan South Railway Station along the Project、Zhengpu Port Station、Hanshan Station will start construction one after another。The main project is expected to be completed by the end of 2025.,It was completed and opened to traffic in 2026。

Chaoma Intercity Railway is a new high-speed railway channel from Anhui to Shanghai and other cities in the Yangtze River Delta.,When completed, it will become Hefei.“One hour commuting circle”An important part of,To further improve the layout of regional high-speed railway network,Enhance the transport capacity of the corridor,It is of great significance to accelerate the development of Wanjiang City Belt.。Da Wan News reporter Liu Yang

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China