Compete with the wind! Zoomlion Crane Helps Set up "Big Windmill" Again on Black Soil

March 11, 2024

Recently,Sijianfang Village, Xiaochengzi Town, Kangping County, Shenyang City,The 130-ton engine room and auxiliary parts were lifted off the ground by Zoomlion's 1800-ton all-terrain crane under the watchful eyes of the crowd.、Rise into the sky,Then at the top of 110 meters above the ground.,Be stably installed on the tower。

Hoisting site

“It's done!This windbreak window period is well grabbed.!”Liaoning Energy Holding Group Kangping 300MWThe person in charge of the wind power project said excitedly.,This past February,The project has exceeded the planned task target.,Install a few more fans.,Expected by the end of March,Installed capacity will steadily exceed expectations,The project will be launched in the first quarter.“A good start”。

Commonly known“Big windmill”A Wind Turbine,Most afraid of encountering windy days during installation,Especially when lifting the cabin with super heavy weight.,If the wind is strong, the risk factor will be high.。The project team selected Zoomlion.ZAT18000HAll Terrain Crane, this.“Stable output”Wind power hoisting artifact,Compete with the wind in this rare window of weak wind,The hoisting of the engine room is completed.。

▲ZoomlionZAT18000HThe all-terrain crane is hoisting.

“Install a fan one day earlier,You can generate electricity for one more day.”。As a famous Liaoning Province,“Tuyere”,The spring breeze in Kangping County is the strongest from late March to the end of April.,The successful lifting cabin of Zoomlion's 1800-ton all-terrain crane also seized the opportunity for the next construction.、Laid the foundation。

It is understood that,A total of 75 Wind Turbines with a single unit capacity of 4 MW will be installed in Kangping 300MW wind power project.,At present, 48 Wind Turbines have been hoisted.,Among them, 37 wind turbines were connected to the grid for power generation.。After the project is put into operation,,It is estimated that the annual average power generation will be about 9.200 million kilowatt hours,Tax payment is about 50 million yuan.,Reduce carbon dioxide emissions by 790,000 tons。

Rise in the wind、Race against the wind,Zoomlion crane will also continue to fight in the front line of construction.,Escort the progress of project construction,Sustainable Energy Engineering for China、Contribution to low-carbon development。

Featured

more

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China