January 31, 2024
In the deep mountains of Rongshui in Guangxi,Baiyunling Wind Farm Phase IV Project is under intensive construction.。
The end of the year is approaching,The clock is ticking,Facing the installation task of 55 Wind Turbines,FromGuangxi Fengzhizi Hoisting Engineering Co., Ltd.、Yingkou Shengfeng Machinery Equipment Leasing Co., Ltd.、Beijing Qixing Anda Installation Engineering Co., Ltd.Three of themSAC24000TCollected here。

Baiyunling Wind Farm is located in karst peak cluster depression.,Surrounded by mountains,The mountain road is winding,Such terrain makes the equipment go up the mountain.、The transition brought great difficulties.。SAC24000TAll-wheel steerable,Minimum Turning Radius 16.2m,Auxiliary drive axle increase torque-increasing device,Maximum gradeability 45%,It can also rotate flexibly in the winding mountain road.,Driving advantages are obvious。

The planned total installed capacity of the project is 100MW,Installed fan unit capacity 5.0MW-6.25MWNot equal,In order to cope with complex wind power installation needs,ThreeSAC24000TAdopt main boom of 78m+Jib 62 m,Working condition of main boom super-lift wind power jib with 270-ton counterweightCarry out construction。



Under the pressure of tight schedule and heavy tasks,ThreeSAC24000TIt also demonstrates efficient disassembly and assembly capabilities.。Variable Mast Technology,The pull plate can be quickly folded in place,The jib was removed in less than an hour.,10% faster than comparable product-20 minutes。Newly developed split-type superlift,Disassembly and assembly time reduced to 1 hour。
PlusDiversified transition schemes and service engineers track and debug the whole process,A series of complex installation and disassembly processes,It can often be done in a day and a night.,It saves valuable time for the whole project.。


First lifting since December 17,At present, the installation task has been completed by 30%。After the project is put into operation, it can provide about 2% of clean energy power every year.6.6 billion kilowatt hours,Increase local tax revenue by about 10 million yuan,Save standard coal 3.20,000 tons,Reducing carbon dioxide emissions 26.50,000 tons,It has good economic and social benefits.。
On December 12th, Asian Construction Equipment Group Co., Ltd. (abbreviated as ACE Group) Xuchang Production Base hosted a delegation of senior clients from The Republic of Tajikistan for an in-depth facility inspection. Guided by the warm winter sun, th
Despite the biting cold of early January, the spirit of international cooperation remained warm and vibrant. On January 5, 2026, three clients from Cameroon traveled thousands of miles to Henan, China, arriving with high expectations for a visit to Asian
Copyright Notice 2002-2026 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China