Recently,MultipleXCMG rice pump TruckAppear in the port city of Rizhao,Completed 9300 cubic meters of pouring volume in 48 hours,Help sunshine“The tallest building”——Rizhao Center Commercial Complex Super High-rise Project,Successful completion of mass concrete pouring of raft。
Rizhao Center Commercial Complex Project is a key project in Rizhao City.,The construction area of the project is 500,000 square meters.,Design height 485 m,When completed, it will become“The tallest building in Rizhao”,Add a new landmark to Shandong。
As a super high-rise building,Sunshine center pouring raftThe thickness is 5 meters,Deepest thickness6.1 meter, Need Concreting 9300m3 at one timeConcrete,ConstructionThe bottom plate is thick,The pouring structure is complex、Long time、The square volume is large,Pouring is extremely difficult.,At the same time, due to the low temperature in winter,,Pump Truck in this constructionReliability、Pumping efficiencyExtremely demanding。
To ensure the quality of the project,The project party and the participating units plan in advance,Several special meetings were held,For mix proportions、Construction organization、Material supply、Contingency plan planning in advance、Careful deployment。After receiving the pouring task, XCMG,Send a service team to the construction site immediately,Make every effort to ensure the orderly progress of the project。
At the construction site,Three sets of XCMG rice quantity pump Trucks are extended in the same way、Day and night,Continuous pouring is about48 hours,Efficient、Stable、PreciseSuccessfully completed the pumping task.,Help the project to achieve the first key node goal。
In the bitter wind.,The service team of XCMG is waiting for the whole scene.,Work closely with users,Fully meet customer needs,The intimate service has won the recognition of the construction party.:“The service staff of XCMG communicated with us about the use of the equipment in a timely manner.,Provide thoughtful service guarantee,Help us to complete the pouring task with high quality and efficiency.。”
It is understood that,The project is expected to be completed in October 2024.,Covers the office、 Hotel 、 Apartment 、Catering、Sightseeing and other functions,After completion, it will become a new landmark of urban commercial development.,Better meet the needs of citizens for a better life。
December 11, 2024,Dongfeng Commercial Vehicle 2025 Annual Partner Conference Held in Chengdu。Based on the final season of 2024,Dongfeng Commercial Vehicle joins hands with more than 600 dealers nationwide、There are more than 1000 representatives of mor
December eleventh,With“WE ARE ONE——A family、One heart、Work together、It's going to work”The 2025 Global Supply Chain Strategic Partnership Conference of China Heavy Truck Group was held in Shandong International Convention a
The other day,Final judgment of the People's Court of Changsha County, Hunan Province,It was found that Anbaituo Trading Co., Ltd. had caused damage to the commercial reputation of Sunward Intelligence.,Its behavior constitutes unfair competition.
December 2,Beijing Party Branch of International Corporation and Construction Machinery Party Branch of China Construction Machinery Corporation、The General Party Branch of China has launched“Forging New Productive Forces and Promoting New Indust
Copyright Notice 2002-2025 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China