Water Conservancy Investment Promotes Major Water Conservancy Project Construction to Reverse Schedule and Catch up with Progress

October 16, 2023

Huasheng Online, October 4(All media reporter Feng Yongcheng correspondent Mao Hui)Today,Construction Site of Songli Embankment of Key Embankment Reinforcement Project (Phase I) in Dongting Lake Area,Workers are carrying out the construction of cement cut-off wall for the levee.。During the National Day holiday,Water Conservancy Investment Company of Hunan Port and Navigation Water Conservancy Group(It is called water conservancy investment for short)Grasp the golden period of construction,Reverse the schedule to catch up with the progress,The company acts as the legal representative of the first phase of the key embankment reinforcement project in Dongting Lake area.、Gumutang Reservoir Project、Dongting Lake Ecological Restoration Pilot Project,Construction workers give up their leave,Stick to the front line,Accelerate project construction。

Construction Site of Lannihu Embankment of Key Embankment Reinforcement Project (Phase I) in Dongting Lake Area,Huge Hydraulic Grab is grabbing the undisturbed soil of the dike body and replacing it with plastic concrete with stronger anti-seepage effect.,So as to improve the anti-seepage ability of the levee.。The first phase of the key embankment reinforcement project in Dongting Lake area is 150 major water conservancy projects of the country.,Include dike heightening、Slope Protection、Foot guard、Slope reinforcement and soft foundation treatment, etc.,After completion, it will greatly enhance the flood control capacity of Dongting Lake area.。

The first unit of Gumutang Reservoir Project will generate electricity this year.。During the National Day holiday,Xia Zhengwu, the leader of the mechanical and electrical installation team of Goumutang Reservoir Project, led dozens of workers.,Shuttle back and forth among dozens of cabinets,Construction workers are working day and night.,Ensure that the first unit generates electricity on schedule。

At present,Power Station of Jumutang Reservoir Project、Lock、The concrete pouring of the sluice and other main buildings and the installation of the radial gate of the sluice have been completed.,Installation of metal structure electromechanical equipment is in full swing,The upper and lower lock heads of the ship lock have been closed.,The cofferdam will be removed soon.,The project in the reservoir area has reached the acceptance conditions for water storage.。

Featured

more

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China