From January to May, Changde completed a fixed asset investment of 3.457 billion yuan in transportation.

June 14, 2023

Come this year,Steady progress in investment in transportation projects in Changde,From January to May,The investment in fixed assets of transportation in the whole city is 34.5.7 billion yuan,Among them, 23% of the investment in expressway construction was completed.5.3 billion yuan、Completed investment in water transport engineering construction 3.1.9 billion yuan、National and provincial trunk line construction completed investment 2.9.2 billion yuan、Completed investment in rural road construction 4.400 million yuan、Completed investment in traffic station construction 0.5.3 billion yuan。The city's traffic completed the provincial assessment investment of about 8.5.2 billion yuan,Accounting for 48% of the annual target tasks.2%。

Yichang Expressway Expansion Project under Construction

yuanshui Grand Bridge Construction Panorama

On the highway,Yichang Expressway Expansion Project Completed Investment 9.2.3 billion yuan,40% of annual plan.13%;Luci Expressway Completed Investment 13.1.3 billion yuan,Accounting for 42% of annual plan.35%;Guanxin Expressway Completed Investment 1.1.7 billion yuan,33% of annual plan.42%。

Port of Deshan

Water transportation,Tokuyama kiloton wharf、Municipal thousand-ton wharf、The upgrading and renovation project of 1000-ton Tianjin and Daijiawan Wharf in Lixian County has been completed.,Among them, the thousand-ton wharf in Gaoshi、The Tokuyama kiloton wharf has been accepted.。Yanzhou Junction Project of Shili Channel、The construction of Qingshan Junction Project is progressing smoothly.,The progress of Chang Niu Channel is in progress.。Tianjin Bulk Cargo Logistics Distribution Center Terminal、The supporting wharf of Taixing Oil Depot in Deshan Port Area has been smoothly promoted。

Zhanggongmiao Lishui Bridge completed and opened to traffic

Trunk highway after reconstruction

In terms of trunk roads,A total of 11 projects of 80 kilometers are planned to be completed this year.,At present, 25 kilometers of three projects have completed the main project.,Accounting for 31% of annual plan.25%,6 projects 48.Construction of 1 km has been started,1 item 5.Six kilometers are ready to apply for construction permits to start construction.,1 item 8.Work permit approval is being processed for 4 km。

Rural roads,The upgrading and reconstruction of rural roads in the whole city completed 153.89 kilometers,Accounting for 40% of the planned completion.4%;Provincial Key People's Livelihood Facts Rural Highway Security Facilities Completed 296 Kilometers,Accounting for 52% of the 564 km of the target mission.4%;General National and Provincial Highway Security Refinement Completed 32.5 kilometers,Accounting for 32% of the 100 km of the target mission.5%。Municipal key people's livelihood facts——Reconstruction of 41 dangerous bridges on rural roads completed、Seven are under construction,Complete the target task of 41 of 100 seats%。

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China