May 19,《New Jinhua-Yiwu Railway Line 3 and 4 and related projects introduced into Jinhua area(Expansion and Reconstruction Project of Jinhua Railway Terminal)Prequalification Announcement of Total Price Contract for Construction of First Commencement Section》Publish。The project will officially start construction in July.,Completed and opened to traffic by the end of 2025。
The expansion and reconstruction project of Jinhua Railway Hub is included《Integrated Development Plan for Higher Quality Transportation in the Yangtze River Delta Region》And other major projects planned by the state.。
The total investment of the project is 25.7 billion yuan.,Including the new Shanghai-Kunming speed line(Winding outside Shanghai and Kunming)、Yiwu-Jinhua Railway(Jinyi three or four lines),And that newly construct Yafan marshalling station、Yangmeitang Railway Freight Center of East China International Intermodal Port and related connecting lines and other projects。
AmongYiwu-Jinhua Railway(Jinyi three or four lines)The design speed is 250 km/Hour。
The implementation of the project will optimize the regional road network in Zhejiang.,Strengthen the passenger and freight transport capacity of the Shanghai-Kunming Grand Passage and the energy level of the railway hub in the central and western parts of Zhejiang Province,Ease channel tension,Effectively release Jin Jian、Jin Yong、Transport capacity of Hangzhou-Wenzhou Railway,Vigorously promote comprehensive transportation“Three laps”Construction。
Schematic Diagram of Expansion and Reconstruction Scheme of Jinhua Railway Terminal
1、Bidding conditions
This project has been approved by《Provincial Development and Reform Commission on the New Jinhua-Yiwu Railway III、The fourth line and related projects introduced to Jinhua area(Expansion and Reconstruction Project of Jinhua Railway Terminal)Reply to the feasibility study report of the project》(Zhe Fa Gai Xiang Zi〔2022〕374)、《Zhejiang Provincial Development and Reform Commission on the New Jinhua-Yiwu Railway III、The fourth line and related projects introduced to Jinhua area(Expansion and Reconstruction Project of Jinhua Railway Terminal)DK0~DK23+Reply to preliminary design of pre-station works of Section 011》(Zhe Fa Gai Xiang Zi〔2023〕Number 111)、《Zhejiang Provincial Development and Reform Commission on the new Hangzhou-Wenzhou Railway Yiwu-Wenzhou Section Yongjia Station Wenzhou End Connection Turnout Adjustment and other 3 itemsⅠLetter of Approval for Class I Design Change》(Zhe Fa Gai Xiang Zi〔2022〕563)Approve construction。
The owner of the project is Jinhua Railway Hub Construction Development Co., Ltd.,China Railway Shanghai Bureau Group Co., Ltd. was entrusted with the construction.。
2、Project scope and division of bid sections
(1)New Jinhua-Yiwu Railway Line 3 and 4DK0~DK23+Length of new main line of Section 001 23.001 kilometers,As well as the introduction of Yiwu Station related Shanghai-Kunming High-speed Railway Liaison Line.、Pre-station works such as connecting line of Jinhua-Ningbo Railway(Excluding the track laying works and the prefabricated and erected simply supported beam works other than the Jinyong connecting line)。
(2)Simultaneous implementation of Hangzhou-Wenzhou Railway Project:Length of Jinhua-Yiwu Railway Line 34 0.483 kilometers,Length of Jinyi-Shanghai-Kunming High-speed Railway Link Line 1.547 kilometers。
Planned duration:28 months,Planned commencement date: July 1, 2023,Planned Completion Date November 1, 2025。
It is divided into 1 bid section,Section number:JYSSXSG-1。The construction and installation cost of the project is about 13.2.4 billion yuan。
In today's complex and changeable international trade pattern,,TIRTransportation is undoubtedly a powerful force to promote the rapid development of international economy and trade.,It is an efficient and smooth way in the global economic context.
November 18,China Railway Material Trade Co., Ltd. and Liugong Owim Co., Ltd. held a discussion and exchange。Secretary of the Party Committee of China Railway Material Trade、Chairman Chen Jinliang,Chen Yupeng, general manager of Owim Company, attended
//// Recently,Sponsored by Cummins East Asia Distribution Division Power SectorGenerator Set Market Dealers MeetingHeld in Fujian。Yu Pingyuan, General Manager of Power Sector of Cummins East Asia Distribution Division、Party Secretary of Chongq
Earnings per share for the third quarter of 2024 was5.06Dollar;Adjusted earnings per share was5.17Dollar; Cash flow from operating activities for the third quarter of 2024 was:3.6 billionDollar; Input in the third quarter1.5 billionCash in US d
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China