May 05, 2023
The reporter learned from the Fuhuai Railway Bid 4 Project Manager Department of the 12th Bureau of China Railway on the 4th.,Construction of Fuyang Section of Fuhuai Railway is progressing in an orderly manner,At present, the total output value is about 16396..30,000 yuan。
Starting and ending mileage of Fuhuai Railway Section 4 of China Railway 12th Bureau Group Co., Ltd.DK105+501.19~DK143+786.39,The terminal is connected to Fuyang West Station.,Across Lixin County, Bozhou City,Yingdong District, Fuyang City、Yingquan district、Yingzhou District,Total length 38.285 kilometers。Among:3 double-track super-large bridges/34.51 kilometers,One single-track super-large bridge/0.72 kilometers,There are totally 8168 bored piles.、1051 piers and abutments、Prefabricated box girder with 990 holes(968 holes of double-track box girder、22 single-track box girders)、15 special structures(High-low tower hybrid cable-stayed bridge 1 unit、Cantilever continuous beam 4-unit、Cast-in-situ continuous beam 4 links、Turnout continuous beam 2 sets、Tied arch 2 holes、Swivel 1 link、Steel structure 1 unit);Section 2 of interval subgrade/0.69 kilometers,Section 1 of station and yard subgrade/1.43 kilometers,Ballastless track bed 52.15 km of track laying。The contract period is 42 months.(September 30, 2022 to March 31, 2026),Contract value 29.6.1 billion yuan,Up to now, the total output value is about 16396..30,000 yuan。
Temporary construction works,Construction access road(Temporary bridge)Accumulative construction access road 6.Six kilometers,The steel trestle across the Cihe River has been completed and put into use.;Mixing station、Laboratory、Reinforcement yard,All of them have been accepted and put into use.;Box girder prefabrication yard,The construction of Fuyang Beam Yard and Yingquan Beam Yard has been completed by about 90%;Commissioning of the mixing station has been completed,Agitation conditions are available,It has passed the preliminary acceptance of the supervision station.;The construction of the office area and the living area has been completed and the office has been settled.。It is expected to enter the trial production stage of box girder through acceptance before May 20.,Before July 25, it passed the box girder certification and entered the formal production.。
Main works,4517 pipe piles for subgrade works have been completed,736 pile foundations of bridge works have been completed,15 pile caps completed。
In today's complex and changeable international trade pattern,,TIRTransportation is undoubtedly a powerful force to promote the rapid development of international economy and trade.,It is an efficient and smooth way in the global economic context.
November 18,China Railway Material Trade Co., Ltd. and Liugong Owim Co., Ltd. held a discussion and exchange。Secretary of the Party Committee of China Railway Material Trade、Chairman Chen Jinliang,Chen Yupeng, general manager of Owim Company, attended
//// Recently,Sponsored by Cummins East Asia Distribution Division Power SectorGenerator Set Market Dealers MeetingHeld in Fujian。Yu Pingyuan, General Manager of Power Sector of Cummins East Asia Distribution Division、Party Secretary of Chongq
Earnings per share for the third quarter of 2024 was5.06Dollar;Adjusted earnings per share was5.17Dollar; Cash flow from operating activities for the third quarter of 2024 was:3.6 billionDollar; Input in the third quarter1.5 billionCash in US d
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China