May 05, 2023
The reporter learned from the Fuhuai Railway Bid 4 Project Manager Department of the 12th Bureau of China Railway on the 4th.,Construction of Fuyang Section of Fuhuai Railway is progressing in an orderly manner,At present, the total output value is about 16396..30,000 yuan。
Starting and ending mileage of Fuhuai Railway Section 4 of China Railway 12th Bureau Group Co., Ltd.DK105+501.19~DK143+786.39,The terminal is connected to Fuyang West Station.,Across Lixin County, Bozhou City,Yingdong District, Fuyang City、Yingquan district、Yingzhou District,Total length 38.285 kilometers。Among:3 double-track super-large bridges/34.51 kilometers,One single-track super-large bridge/0.72 kilometers,There are totally 8168 bored piles.、1051 piers and abutments、Prefabricated box girder with 990 holes(968 holes of double-track box girder、22 single-track box girders)、15 special structures(High-low tower hybrid cable-stayed bridge 1 unit、Cantilever continuous beam 4-unit、Cast-in-situ continuous beam 4 links、Turnout continuous beam 2 sets、Tied arch 2 holes、Swivel 1 link、Steel structure 1 unit);Section 2 of interval subgrade/0.69 kilometers,Section 1 of station and yard subgrade/1.43 kilometers,Ballastless track bed 52.15 km of track laying。The contract period is 42 months.(September 30, 2022 to March 31, 2026),Contract value 29.6.1 billion yuan,Up to now, the total output value is about 16396..30,000 yuan。
Temporary construction works,Construction access road(Temporary bridge)Accumulative construction access road 6.Six kilometers,The steel trestle across the Cihe River has been completed and put into use.;Mixing station、Laboratory、Reinforcement yard,All of them have been accepted and put into use.;Box girder prefabrication yard,The construction of Fuyang Beam Yard and Yingquan Beam Yard has been completed by about 90%;Commissioning of the mixing station has been completed,Agitation conditions are available,It has passed the preliminary acceptance of the supervision station.;The construction of the office area and the living area has been completed and the office has been settled.。It is expected to enter the trial production stage of box girder through acceptance before May 20.,Before July 25, it passed the box girder certification and entered the formal production.。
Main works,4517 pipe piles for subgrade works have been completed,736 pile foundations of bridge works have been completed,15 pile caps completed。
December 11, 2024,Dongfeng Commercial Vehicle 2025 Annual Partner Conference Held in Chengdu。Based on the final season of 2024,Dongfeng Commercial Vehicle joins hands with more than 600 dealers nationwide、There are more than 1000 representatives of mor
December eleventh,With“WE ARE ONE——A family、One heart、Work together、It's going to work”The 2025 Global Supply Chain Strategic Partnership Conference of China Heavy Truck Group was held in Shandong International Convention a
The other day,Final judgment of the People's Court of Changsha County, Hunan Province,It was found that Anbaituo Trading Co., Ltd. had caused damage to the commercial reputation of Sunward Intelligence.,Its behavior constitutes unfair competition.
December 2,Beijing Party Branch of International Corporation and Construction Machinery Party Branch of China Construction Machinery Corporation、The General Party Branch of China has launched“Forging New Productive Forces and Promoting New Indust
Copyright Notice 2002-2025 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China