In order to implement 33 policies and measures to stabilize Tianjin's economy in the first quarter,,Accelerate the construction progress of Tianjin-Weifang high-speed railway,Recently,Tianjin Transportation Commission、Working group jointly formed by Tianjin Development and Reform Commission and other departments,The on-site office meeting was held in the project department of the first section of the Tianjin-Weifang high-speed railway constructed by the 14th Bureau of China Railway.。
At the office meeting,Tianjin Transportation Commission、Tianjin Development and Reform Commission and other units highly appraised the progress of the project construction of the 14th Bureau of China Railway.。The meeting pointed out,Tianjin-Weifang high-speed railway Project of China Railway Shisiju Group Co., Ltd.,The preliminary work is tense and efficient.、Scientific and powerful construction organization guarantee、Smooth and orderly resumption of work and production,To achieve the first quarter“A good start”Lay a solid foundation。
The First Section of Tianjin-Weifang high-speed railway undertaken by China Railway No.14 Engineering Group Co., Ltd,Located in Tianjin Binhai New Area,It mainly includes the Jingu Haihe Tunnel.、One subgrade section,The total length is nearly 7.Five kilometers。This construction section is the key project of the whole line of Tianjin-Weifang high-speed railway.,The scale of the project is large、A large number,Difficult in project organization and management。
Since the approach,The project team insists on planning first.,Complete the Pre-project planning at the fastest speed;Adhere to“Build a win-win situation”The guidelines for,Promote the early requisition and demolition work with high efficiency;Highlight the key and difficult points,Strengthen the management and control of key work nodes;Implement“Three modernizations and one new”,High-standard construction of high-quality projects in the era。
First quarter of 2023,Excellent achievements in many aspects on the whole line,Realized“Take the lead at the start of the race、Start sprinting”A good situation。
01 The first laboratory of the whole line to pass the acceptance
January 10,The central laboratory of the project department has successfully passed the evaluation and acceptance of the owner and the supervision unit.,It marks that the laboratory has become the first central laboratory that has successfully passed the acceptance test among all the participating construction units in Jinwei high-speed railway.,The conditions for carrying out the test and inspection work have been met.。The area of the laboratory is about 1650 square meters.,It is divided into office areas、Three functional areas of test operation area and living area。
02 The first new project site that has passed the acceptance and settled in the whole line
January 10,The construction of the project site has been completed and passed the acceptance.。11,The residence of the project department is settled.,It has become the first new project site in Jinwei high-speed railway to pass acceptance and be settled in.。
03 Undertake the first party building cloud class on the whole line
January 16,The Party Branch of Tianjin Command of Xiongan high-speed railway Company organized a cloud classroom activity for Party building in Tianjin and Weifang high-speed railway.,As the main venue, the conference room of the project department undertakes the first party building cloud class of the whole line.。
04 The first steel bar processing plant completed on the whole line
January 17,Completion of construction of steel bar processing plant of the project,It has become the first steel bar processing plant completed on the Tianjin-Weifang high-speed railway line.。
05 The first bid section of the whole line to complete the test pile
January 18,The first pile test of the project was successfully completed,It has become the first unit to complete the test pile on the whole line of Jinwei high-speed railway.。
06 The first mixing station of the whole line to pass the acceptance
January 18,The construction of the mixing station of the project has been completed and passed the acceptance,Become the first mixing station that has passed the acceptance of the whole line。
After the completion of Tianjin-Weifang high-speed railway,,It can complement Beijing, Tianjin and Hebei、Short board of high-speed railway development in coastal areas such as Shandong Peninsula,In the regional road network, a new high-capacity fast track will be formed in the eastern part of the Beijing-Shanghai high-speed railway.,Greatly enhance the Yellow River Delta and Beijing-Tianjin-Hebei、The interconnection level of the Yangtze River Delta and other urban agglomerations。
(China Railway 14th Bureau)
December 11, 2024,Dongfeng Commercial Vehicle 2025 Annual Partner Conference Held in Chengdu。Based on the final season of 2024,Dongfeng Commercial Vehicle joins hands with more than 600 dealers nationwide、There are more than 1000 representatives of mor
December eleventh,With“WE ARE ONE——A family、One heart、Work together、It's going to work”The 2025 Global Supply Chain Strategic Partnership Conference of China Heavy Truck Group was held in Shandong International Convention a
The other day,Final judgment of the People's Court of Changsha County, Hunan Province,It was found that Anbaituo Trading Co., Ltd. had caused damage to the commercial reputation of Sunward Intelligence.,Its behavior constitutes unfair competition.
December 2,Beijing Party Branch of International Corporation and Construction Machinery Party Branch of China Construction Machinery Corporation、The General Party Branch of China has launched“Forging New Productive Forces and Promoting New Indust
Copyright Notice 2002-2025 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China