Products Center
More Products

Zoomlion Crane Escorts Construction of Xinjiang Mulei 500 MW Wind Power Project

January 20, 2023

Recently,Xinjiang Mulei 500MWWind Turbine hoisting of wind power project is fully completed,Zoomlion Crane sticks to the front line of the project,Towering wind towers have been erected in the vast frontier.。

Xinjiang Mulei Wind Power Project is located in Mulei Kazakh Autonomous County, Xinjiang.,It is a wind power project group consisting of five wind farms,Total installed capacity 500MW,Unit capacity 2.5MW,It includes a large stone wind field located in the eastern mountainous area of Mulei County.(120 steel tower fans);Laojunmiao Wind Farm in the Gobi Desert in the west of Mulei(80 steel-mixing fans)。Xinjiang Mulei Wind Power Project completed hoisting of 200 Wind Turbines in 5 months,Total lifting weight 11.40,000 tons,It is the largest wind power hoisting construction project contracted by China Nuclear Machinery Engineering in recent years.,Multiple indicators(Including the contract amount、Number of fans、Total weight of hoisting fan, etc.)All of them have refreshed the company's historical records.。

Since its preparation in July 2020,CNNC Mechanical Engineering Workers Face the Upsurge、The temperature difference between day and night is large、The geographical environment is harsh、Lack of supplies、Epidemic、Gale、Extremely cold、There are many difficulties such as the limit compression of the construction period.,In the vast frontier,Until 27 December,In just five months.,Completed Xinjiang Mulei 500MWHoisting of all 200 Wind Turbines in the wind power project,The total hoisting weight reaches 11.40,000 tons。

120 sets!Xinjiang Mulei Dashitou Wind Farm

Until 13:00 on December 24, 2020,Xinjiang Mulei Dashitou Project has only three wind turbines that have not yet been hoisted.,Weather forecast“On December 24, the wind speed at the scene reached 14 meters.,The temperature dropped to minus 18 degrees at night.,December twenty fifth-On December 26, the big stone area will begin to calm down around 15 noon on the 25th.、The wind will rise at 15 noon on the 26th.”,Facing a window period of only 24 hours,How to complete the hoisting of the last three wind turbines on schedule,Become the biggest problem at present。China Nuclear Machinery Engineering Xinjiang Mulei Dashitou Project Department held an emergency site temporary coordination meeting.,In order to make full use of the only lifting window period,Ensure that the project is completed on schedule,The project department must complete the construction tasks such as the assembly of two main cranes and the hoisting of the engine room before 6 o'clock on the 26th.,Complete all the remaining wind turbine hoisting construction tasks before the wind starts on the 26th.。

Overall arrangement of Dashitou Project Department,Each working face shall organize the staff to actively work overtime to assemble the main crane.,Carry out hoisting preparation and wind turbine hoisting under the condition of time surplus.;The personnel of the project department and the external labor service personnel are the second echelon to replace at any time.,Ensure continuous construction,Ensure that the engine room is hoisted and the impeller is assembled within 24 hours.。At the same time,The logistics support team provided mutton and other meals to the scene in time.,The coordination group shall organize shift personnel to enter the site in time.,Work on site in an orderly manner。At 20:00 on 24 DecemberFAssemble the main crane at 44th position、The hoisting of the engine room was completed at 22:08 on December 25.,Complete the lifting of the impeller at 13:05 on the 26th;FMachine 50 completed the main crane assembly at 4:48 on December 25.,The hoisting of the engine room was completed at 4:28 on December 26.,Impeller completed at 15:23;FUnit 49 completed the impeller assembly at 0:23 on the 26th,Complete the lifting of the impeller at 13:00。At this point,Finally, the hoisting of all three wind turbines is completed.。

80 units!Xinjiang Mulei Laojunmiao Wind Farm

Weather forecast for December 26, 2020,“On December 27, the Laojunmiao area in Mulei County, Xinjiang, will begin to blow around 12 noon.”,Faced with sudden changes,The project still has 9 wind turbines that have not been hoisted.,Closing node approaching on December 28,Once you miss the hoisting time window on the 27th,,It will be extremely difficult to guarantee the completion of the progress node target.。China Nuclear Machinery Engineering Xinjiang Mulei Laojunmiao Project Department held an emergency site temporary coordination meeting,Speed up the construction progress,Make full use of the hoisting window period from the evening of the 26th to the early morning of the 27th,Complete the hoisting construction tasks of the remaining 9 wind turbines before the wind starts on the 27th。

During the daytime on December 26, the National New Tianli was completed successively.GXNo.19 wind turbine and Silk Road DachengDCHoisting of No.18 fan,1:34 am on the 27th,The temperature dropped to-17 degrees,Complete Puleihai Wind Power ProjectPLHHoisting of No.22 stand;2:32 a.m,The temperature dropped to-23 degrees,Silk Road DachengDCCompletion of hoisting of No.20 stand...13:32,Guoxin TianliGXThe fan at position 20 was successfully hoisted in place.,At this point,The hoisting of the last 9 wind turbines was completed in 26 hours.。

Xinjiang Mulei 500MWWind power projects can achieve excellent results.,It is inseparable from the staff who are fighting in the front line.。The low temperature environment in winter is a severe challenge to mechanical equipment and personnel.,Under the threat of winter gales,The smooth and early completion of the project is the result of the joint efforts of all.。It is a group of project builders who are not afraid of the cold.,Brave the wind and snow,Work tirelessly in the vast desert,Deliver electricity to thousands of families、Warm,Light the lights of reunion。Let's pay tribute to the workers who are fighting in the front line.,Zoomlion cranes will also continue to accompany the builders.,Building a Beautiful China Together!

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China