October 14, 2022
1—September,Bazhong Section of Cangba expressway Completes Investment 37655..90,000 yuan,Accounting for 188% of the annual investment task.3%。Image progress:Cumulative 11419 of tunnel excavation.m,Account for 12899 that totalm88.53%;Subgrade earthwork excavation completed accumulatively 385.140,000m³,Total 765 completed.730,000m³50.3%;Subgrade filling completed accumulatively 182.130,000m³,Total completed 489.230,000m³37.2%;A total of 1656 bridge pile foundations have been completed.,69% of total 2382 pieces completed.5%;619 tie beams,Completed 48% of the total 1278 tablets.4%;555 piers,Completed 34% of the total 1617.3%。
【Source:Bazhong Traffic Bureau_Work dynamics】