Vulcan mountain hospital was built in 10 days to see the Chinese speed behind the construction machinery

June 19, 2020

China is always well protected by their bravest people.

& mdash; & mdash; Kissinger

On February 2, 2020, the " Vulcan Mountain Hospital was officially completed " good news swept across the network. In 10 days, a hospital with a capacity of 1,000 beds was officially completed. Vulcan Mountain Hospital, with a total construction area of ​​34,000 square meters, was built with reference to the Xiaotangshan Hospital in Beijing during the SARS period in 2003, and is used to treat patients with pneumonia infected by the new coronavirus. The speed of China reflected in the construction of Vulcan Mountain Hospital is even more praised by people around the world.

Fujian's patriotic situation responds quickly

On January 23, 2020, Wuhan Urban Construction Bureau convened a special conference to focus on the construction of the Third Bureau, and requested to build an emergency hospital in Wuhan based on the model of Xiaotangshan Hospital in Beijing during the 2003 SARS fight. Mountain Hospital. Vulcan Mountain Hospital has a construction area of ​​34,000 square meters and can accommodate 1,000 beds. Construction has begun on January 24, and it was delivered on February 2 in only ten days. Patients were officially admitted on February 3. The Lei Shenshan Hospital was selected in the Huangjiahu area of ​​Jiangxia, with 1,500 new beds and a construction area of ​​about 75,000 square meters. It is expected that patients will be officially admitted on February 6.

& nbsp; & nbsp;

It is incumbent on the country to have difficulties. In this national resistance, the various construction machinery companies have the courage to take the responsibility, organize local enterprises without compensation, convene the available equipment and robots to stand by at any time, and actively participate in the projects to assist in the construction of Vulcan Mountain and Thunder Mountain. among. In times of crisis, only national enterprises can assume the national responsibility and stand up the backbone of the nation. In this emergency aid construction project, domestic engineering machinery brands have exerted unprecedented strength and assumed most of the construction tasks. As the first brand of domestic chassis pump Trucks, Renesas Heavy Machinery also responded quickly and took on heavy responsibility in construction tasks such as Wuhan's Vulcan Mountain and Thunder Mountain.

& nbsp; & nbsp;

In the Vulcan Mountain and Lei Shenshan assistance construction projects, domestic construction machinery and equipment played a major role with their excellent performance and efficient operating conditions, using the veritable "Made in China" to create an amazing "China speed". !!

Race with time

& nbsp; & nbsp;

& nbsp;

& nbsp;

Express report: School of Vulcan Mountain Construction

& nbsp;

On January 24, New Year's Eve, land leveling began.

& nbsp;

On January 25, the first day of the new year, concrete hoisting equipment began to be prepared.

& nbsp;

In the early morning of January 26, Renesas Heavy Machinery set up by Foton Renesas Heavy Machinery and strategic customers and Hubei agents with concrete and hoisting equipment, operators, and service technical teams was established by Wuhan Vulcan Mountain Hospital. The vanguard team arrived at the Caidian site in Wuhan and quickly invested in the concrete floor laying project of Vulcan Mountain Hospital. At the same time, in order to ensure the normal operation of the construction equipment 24 hours a day and night, Renesas Heavy Machinery dispatched a number of experienced service engineers to the site to stand by and be on call 24 hours a day to escort the project construction.

& nbsp;

On January 27, site leveling and gravel yellow sand backfilling were all completed, and the first batch of box container board houses were hoisted.

& nbsp;

On January 28, the foundation concrete of the box-type slab houses in the northern area of ​​Vulcan Mountain Hospital was completed, and the concrete pouring of the box-type slab houses in other areas was fully launched. At the same time, another Renesas heavy machine "Lord Pioneer" was assembled and rushed to the construction site of Thunder God Mountain.

& nbsp;

On January 29, the installation of more than 300 box-type board room skeletons was completed, and the electrical and mechanical pipeline operations were started simultaneously.

& nbsp;

On January 30, the laying of HDPE membrane was fully completed, and the equipment of the sewage treatment room was hoisted simultaneously.

& nbsp;

On January 31, 90% of the container assembly was completed, and the skeleton of the mobile board room was installed to 3,000 square meters.

& nbsp;

On February 1, the concrete pouring has been completed, and the movable panel room has been completely installed. The medical equipment installation has been fully launched.

On February 2, Vulcan Mountain Hospital was officially completed and delivered.

& nbsp; & nbsp;

Behind the amazing Chinese speed is the hard work of countless engineering builders. The time is tight and the task is heavy. The pump Truck workers at the scene cooperate with each other. One Vehicle matches 2-3 people. The 24-hour "three shifts" system is implemented. For a few days, construction workers could only stand in the temporary board room or even by the roadside, hurriedly finished with boxed lunches, and started construction. The pump cab also became a common shop for them to sleep, only sleeping for two or three hours a day.

& nbsp; & nbsp;

Corresponding to this are complex working conditions and scheduling difficulties. Under such a huge project, there are many people, many equipment, and different types of work, and the construction workers are facing multiple pressures such as the Spring Festival holiday, severe epidemic situation, and difficult conditions. The construction is not very smooth. Many on-site emergencies require solutions. Settle on the spot. However, the front-line project builders overcame it with a strong will and the feelings for the country and the people, and they are also the heroes of this anti-epidemic war!

Non-stop construction in advance

In this construction project of Wuhan Vulcan Mountain Hospital, Renesas Heavy Machinery successfully completed its mission.

& nbsp; & nbsp;

As a participant in the construction of Vulcan Mountain and Lei Shenshan Hospital, Hubei Xinliheng has a variety of brands of construction machinery and equipment, and ultimately chose to dispatch Renesas equipment to support the hospital's infrastructure concrete construction tasks. Introduced to:

This task is a national project. The required construction period is very tight and the site conditions are poor. Because it is the construction of multiple temporary mobile homes, it will involve a number of pumping tasks in small quantities and multiple times. What matters are the long-term stability of the Renesas pump Truck, the mobility of the chassis, and the precise pumping ability.

Daily Reesa 58-meter pump truck KT010492 daily data statistics table

(Data from Renesas Connected Cars)

Time

Startup time (hours)

Pump volume

Comprehensive fuel consumption (L / square)

January 26

10.5

216

0.46

January 27

12.8

392

0.49

January 28

23.4

298

0.4

January 29

23.3

671

0.31

January 30

14.9

167

0.37

January 31

13.8

288

0.3

February 1

16.1

61

0.5

Take the Renesas KT010492 pump truck participating in the construction of Vulcan Mountain as an example: As of February 2, the completion of Vulcan Mountain, the data of the Renesas Heavy-Duty Locomotive Networking Platform shows that the Renesas KT010492 pump truck runs from January 26 to February 1, Continuous working for 7 days, continuous non-stop time of 114.8 hours, a total of 2093 cubic meters of pumping volume, and an average fuel consumption of only 0.4L cubic / day. Among them, the start-up time on January 29 reached 23.3 hours, and the pumping volume per day was 671 square meters.

& nbsp; & nbsp;

Histogram of daily startup time of 58-meter pump truck KT010492 on Vulcan Hill Reza

& nbsp; & nbsp;

Histogram of daily Concrete Pumping volume and fuel consumption of 58-meter pump truck KT010492 on Vulcan Mountain Reza

& nbsp; & nbsp;

Histogram of average daily fuel consumption of 58-meter pump truck KT010492 on Vulcan Mountain Reza

& nbsp; & nbsp;

Vulcan Mountain Pump Truck KT010492 & nbsp; & nbsp; Screenshot of Sampling Data of Vehicle Networking Background on February 1

& nbsp; & nbsp;

Vulcan Hill Reza 58m pump truck KT010492 & nbsp; & nbsp; Screenshot of the sampling data of the Internet of Vehicles on February 1

As the main equipment for pouring concrete into the foundation of Vulcan Mountain Hospital, the 58-meter pump truck of Renesas Heavy Machinery requires continuous operation without stopping the entire project cycle. In a variety of complex construction environments, with a stable chassis and precise Concrete Pumping capacity, continuous non-stop operation for an extended period of time, to a certain extent, improve the efficiency of construction work, ensure the quality of the foundation project, and help the project The team completed the delivery of Vulcan Mountain Hospital 1 day in advance!

Retha ’s 58m pump truck kt004780 Lei Shenshan construction data

(Data from Renesas Connected Cars)

Time

Startup time (hours)

Pump volume

Comprehensive fuel consumption (L / square)

January 27

11.3

214

0.45

January 29

20.6

206

0.43

January 30

23.95

172

0.55

January 31

22.65

336

0.46

February 1

22.95

344

0.52

February 2

10.2

36

0.53

Renesas pump truck also plays an important role in the construction of Thunder Mountain Hospital. Take the Renesas KT004780 pump truck participating in the construction of Lei Shenshan as an example: As of February 2, the data of the Renesas heavy-duty locomotive networking platform shows that the Renesas KT004780 pump truck has been working continuously from January 27 to February 2. For 6 days, the continuous non-stop time reached 111.5 hours. The total pumping volume was 1308 cubic meters, and the average fuel consumption was only 0.47L cubic / day.

& nbsp; & nbsp;

Histogram of the daily start-up time of Raytheon KT004780 Renesas 58m pump truck

& nbsp; & nbsp;

Daily volume and fuel consumption chart of KT004780 Renesas 58-meter pump truck in Thunder Mountain

& nbsp; & nbsp;

Histogram of the daily average fuel consumption of the 58-meter pump truck of Lei Shenshan KT004780 Renesas

& nbsp; & nbsp;

Screenshot of the sampling data of the background of the Internet of Vehicles on the February 2nd of the Thunderbolt KT004780 pump truck

& nbsp; & nbsp;

Screenshot of the sampling data of the background of the Internet of Vehicles on the February 2nd of the Thunderbolt KT004780 pump truck

According to the data, the Renesas pump trucks that participated in the construction of the Wuhan Emergency Hospital all reflected the high reliability of continuous work and non-stop during construction, as well as the reduction in the number of refueling trips due to low fuel consumption. Efficiency, the advance delivery of Vulcan Mountain, the pump truck products of Renesas Heavy Machinery contributed a lot.

After the successful completion of Vulcan Mountain Hospital, Renesas Heavy Machinery will continue to support the construction of Lei Shenshan Hospital and other local epidemic prevention projects, race against time, show the strength of China manufacturing, and make use of the domestic chassis The strength of the first brand of pump trucks builds a strong shield for winning the epidemic defense war.

& nbsp; & nbsp;

The Brave Retrogrades

The battle & ldquo; epidemic & rdquo; is not over yet

Reza will continue to rush forward

To overcome the difficulties with the people of the motherland

Construction Machinery Online

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China