June 07, 2020
On the afternoon of February 1, the foundation construction of wuhan vulcan mountain hospital project site, which was jointly constructed by wuhan construction engineering, wuhan hangfa and hanyang municipal administration, was completed, and 1650 sets of containers were installed, more than 90% of which were assembled on site. The frame installation of mobile board room (medical technology building, ICU ward) has been completed.
From January 25 to February 1, more than 7,000 constructors worked hard, raced with the plague and demons to achieve the key point in eight days. Wuhan vulcan mountain hospital was completed today.
full access to medical equipment installation
On the morning of February 1, the first CT machine entered the medical technology building of wuhan vulcan mountain hospital and began to install. It is reported that related medical equipment is coming into the field to install and debug.
According to the introduction of the third bureau of China construction engineering co., LTD., it has now entered the stage of medical equipment installation, including water, electricity, heating and ventilation equipment, oxygen supply system and other installation of 1,200 sets, 70% completed; Pipeline trench excavation, embedding and backfilling 95% completed; Hoisting of sewage treatment station equipment is completed; Pipeline installation 95% completed; Concrete pouring of rainwater regulating cistern floor is completed; Equipment installation completed 60%; Construction of septic tank foundation completed; The installation of integrated rainwater lifting pump is completed; Interior decoration supporting, outdoor medical supporting projects, etc.
Wuhan vulcan mountain hospital has a total construction area of 60,000 square meters, of which 34,000 square meters are newly built isolation zones. There are 419 wards and 1,000 beds (including 30 ICU intensive care wards).
gigabit fiber assisted video consultation
On the evening of January 31, China telecom assisted the PLA general hospital and wuhan vulcan mountain hospital to successfully set up the remote consultation application system, which will help the PLA general hospital to conduct video consultation with wuhan vulcan mountain hospital through gigabit optical fiber network.
According to the current construction requirements, wuhan telecom set up 20 commandos and completed the remote consultation system in less than 12 hours. Under the situation of pneumonia prevention and control of new coronavirus infection, the timely deployment of medical resources of major hospitals to help the treatment of difficult diseases remotely can make the diagnosis and treatment of the epidemic situation more efficient, convenient and safe.
radiological protection detection
On February 1, wuhan occupational disease prevention hospital sent a team of four experts to wuhan vulcan mountain hospital to conduct quality control and radiological protection test on the CT room and other radiological diagnosis and treatment equipment in order to put it into use. Liu ansheng, director of the radiological health department of the city's occupational-disease-prevention hospital, said they received the letter from vulcan mountain hospital to carry out an emergency radiological protection test. We in wuhan are united as one, united as one, we will win the battle of epidemic prevention and control! Throughout the &;
half of the hospital will be covered with flowers and trees
On the afternoon of February 1, the reporter of changjiang daily contacted the person in charge of the vulcan mountain emergency project greening site, and was informed that at 8 PM on the 1st, the greening battle of vulcan mountain hospital was officially started. Papers & throughout; .
According to the introduction, the vulcan mountain hospital covers an area of about 82,000 square meters, including nearly 40,000 square meters of green construction area. That is to say, in the future, half of the whole hospital will be covered with flowers and trees.
Wu zhaoyu, who is in charge of the greening scheme design, explained that the vulcan mountain hospital was an emergency project, and as a temporary greening project, it borrowed some experience from xiaotang mountain. Mainly through afforestation, play the role of beautification environment and appropriate isolation, let patient and medical worker can relax mood.
At present, about 30 trees, 2200 shrubs, tens of thousands of square meters of grass and other seedlings and ground cover plants needed for the construction of vulcan mountain hospital greening project have been basically stored in place. Seedlings and Vehicles are thoroughly disinfected before going out.
24-hour power supply guarantee team set up
& other; I volunteer to join the vulcan mountain hospital power supply security team, listen to the party command, strictly observe the discipline, do a full 24 hours of power guard work! Throughout the &; On the morning of February 1, the power supply pledge division of power supply company of wuhan caidian district of state grid vulcan mountain hospital was held in the power supply guarantee headquarters of vulcan mountain hospital.
With the power supply of vulcan mountain hospital on January 31, the hospital construction project is coming to an end. In order to ensure that the hospital power supply continues normal and reliable, get through “ Green medicine in a race against time ” Power channel, state grid wuhan caidian district power supply company set up the on-site epidemic prevention and power protection headquarters, set up the vulcan mountain hospital power supply security team, 24 hours uninterrupted stay to protect power.
the first group of property personnel stationed
At 4:20 p.m. on February 1, the first group of 25 property logistics personnel stationed in the vulcan mountain hospital arrived at the hospital life and work area positions. They came from vanke, huizhimei and your court three property companies.
According to the city housing authority vulcan mountain, Raytheon mountain hospital property management work special class introduction, hospital life and work area cleaning and killing work completed on the evening of 1, 2 early morning into the hospital to carry out work.
air conditioning water heater TV set medical equipment and facilities first-class
By 6 PM on February 1, the 1,000-bed vulcan mountain hospital had installed medical equipment with 400 beds. Today, all the 1,000-bed medical equipment was installed in place.
Reporter spot sees, by the most south is a U shape of two storeys to live in hospital building, it is to install with container. To the north is a row of mobile board houses, mainly used for medical buildings, ICU wards. Around the two - story residential building and mobile board room, is a circular road, is currently working overtime to pave. The circular road around the inpatient building has been laid. The road is about 3 meters wide and covered with concrete and protective film.
At 2 PM, the reporter went deep into the two-story inpatient building (u-shaped building) to visit, the main structure of the building has been completed, the inside is under construction. The building has two floors, each with three corridors. The middle corridor is about 2 meters wide, with wards on both sides.
The reporter saw that every two wards combined a suite. From the inner corridor, there are workshops for the medical staff, and then two wards on either side, each with two beds. Each ward has a separate small window and a glass window. There is also a window facing the corridor. The air conditioning in the ward, window facilities, disinfection equipment are all installed in place. Each ward has a bathroom, and each bathroom is equipped with a water heater.
Reporter saw in one of the wards, wuhan kebei company is installing the room's medical equipment, is oxygen tube, negative pressure tube and supporting equipment. The company site responsible for the introduction of manager li, by the afternoon of 2 will be all installed. & other; The equipment is top-notch. Strictly in accordance with relevant international standards. Throughout the &;
About 5 p.m., the reporter learned that some ward began to install and adjust television, can watch more than 20 channels. Source: changjiang daily
Recently,Good news from Ningtiaota Coal Mine of Shaanxi Coal Group,China Railway Equipment GroupEJM315/4-2FIntelligent Rapid Tunneling Equipment CreatedLow power and short type(Cutting motor power 315kw)Digging and anchoring integrated machine sem
“Hot”The fourth quarter of the war Increase production capacity Expanding the market, promoting R & D and improving efficiency, Zhonglian Agricultural Machinery is firmly moving forward, showing a new trend of vigorous and
November 21, 2024,As an important partner,Party Secretary of Shaanxi Construction Machinery Co., Ltd.、Chairman Yang Hongjun was invited to attend the celebration of the 12th anniversary of the founding and development of Anhui Liju Group and
November 19-21, local time,Chinese President Xi Jinping pays state visit to Brazil。 Follow the steps of President Xi Jinping,Today,We walked into Trinity Brazil together.。 Back in 2007,Sany Heavy Industry Co., Ltd. was registered in Sao Pa
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China