June 06, 2020
The first special hospital under construction for treating pneumonia patients infected with the new coronavirus was opened in the early morning of July 1 after builders worked around the clock. & ndash; Wuhan vulcan mountain hospital completed the electrical engineering construction, smooth power supply.
On the evening of January 31, the construction site of the vulcan mountain hospital by zhiyin lake in caidian district, wuhan city, was filled with excitement. A few days ago, it was still full of weeds. Now, the party flag flying high, builders on the site sweat.
At 23:49 on January 31, the power supply indicator lights of the power equipment on the site flashed alternately, and 24 box-type transformers set up for the hospital were connected to the wuhan power grid with a beep and started live operation.
Since receiving the construction task on January 23, more than 200 constructors from the wuhan power supply company of state grid have successfully completed the migration of two 10-kv lines, installation of four ring-grid cabinets and 24 box-type transformers, and deployment of supporting cables in about a week, overcoming the impact of severe weather on the construction.
According to hu hao, general manager of wuhan caidian power supply company of state grid, who was in charge of the on-site command, the vulcan mountain hospital adopted the design of dual power supply, which can ensure the stability of power supply to a large extent.
In terms of civil engineering, wuhan vulcan mountain hospital project has completed site leveling, sand and stone backfilling, film laying and other aspects of the construction. Board room hoisting is advancing rapidly.
previous reports: 7 km of cable set up in 3 days
At about 1800 hours on 29 January, a special hospital was under construction to treat pneumonia patients infected with the new coronavirus. & ndash; Wuhan Raytheon mountain hospital electric power supporting project completed the construction of smooth power. More than 300 builders worked around the clock to complete the installation and commissioning of 7km of high-voltage cables and 26 equipment in just three days.
In the evening, at the site of Raytheon mountain hospital by huangjia lake, jiangxia district, wuhan city, with the order of the field project leader, Raytheon mountain hospital was connected to wuhan power grid via a 10-kv line and began live operation.
According to Chen gang, general manager of wuhan jiangxia district power supply company of state grid, the four-loop design of double power supply for Raytheon mountain power facilities can largely ensure the reliability of hospital power supply.
After receiving the notice of the construction of Raytheon mountain hospital on January 25, the wuhan power supply department set up a party branch on the construction site, detailing the safeguard measures and fully promoting the construction of the power project, so that the party flag flew high on the construction site. More than 300 commandos according to the The epidemic is the order. , and promptly completed the transmission task.
At present, the project civil engineering is still under construction. It is understood that the location of wuhan Raytheon mountain hospital in the city jiangxia district huangjia lake. According to the latest design, the total floor area of the hospital has been expanded to about 60,000 square meters. Among them, medical isolation area about 51,000 square meters, the number of beds increased to about 1,600; The medical and nursing accommodation area is about 90,000 square meters and can accommodate more than 2,000 medical and nursing staff.
Collated according to customs data,In October 2024, China's import and export trade volume of construction machinery was 48.$4.1 billion,Year-on-year growth of 24.2%。Among:Imports 2.$3.3 billion,Year-on-year growth of 33.1%;Exports 46.$0.8 billion
Guangxi Cummins,Zan 8 Review of past issues
November 20,Party Secretary of Shandong Heavy Industry Group、Chairman Man Shengang Meets with ZF Group Board Members、Peter, Head of Commercial Vehicle Solutions and Industrial Technology·Lyle,The two sides exchanged views on further deepening st
November twenty sixth-The 29th, bauma CHINA 2024 Yingxuan Heavy Industry Booth W5.511 Look forward to your visit. Witness the glory of construction machinery industry with us! ▌Plea
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China