June 05, 2020
On January 27, at zhiying lake, caidian district, wuhan city, the beach grass slope covering an area of 50,000 square meters was completely changed. Iron hand & throughout; In a corner of the site up and down flying, four working areas have been laid in a white nonwovens do impervious. Conference room, 4th floor, project headquarters building, “ Vulcan mountain hospital emergency engineering design disclosure meeting ” It's under way. On the same day, almost all the staff interviewed by reporters are confident to complete the hospital construction on time.
nearly 3000 men in 24-hour shift combat
The workers are installing a high voltage box. Wang yingchun/photography
Vulcan mountain hospital is called wuhan version “ Xiaotangshan & throughout; , special construction to solve the problem of lack of beds for patients with the new type of pneumonia, thus received national attention. On January 23, the same day that wuhan was closed, the wuhan new pneumonia prevention and control headquarters decided to build a new special hospital in the non-main city area near the wuhan sanitarium for workers by the side of caidian zhiyin lake, following the model of xiaotangshan in Beijing.
According to the reporter's on-site verification, the current project has four main construction units: China construction third engineering bureau co., LTD. (hereinafter referred to as ldquo; China construction third bureau Wuhan hanyang municipal construction group co., LTD. (hereinafter referred to as ldquo; Hanyang municipal administration ” Wuhan construction engineering group (hereinafter referred to as ldquo; Wuhan construction ”) Wuhan airport development group co., LTD. (hereinafter referred to as ldquo; Wuhan hangfa ”) , the main design unit is citic architectural design research institute co., LTD. (hereinafter referred to as ldquo; Citic design ”) .
The above 5 units enter the site time is concentrated in January 24 (New Year's eve), in order to mobilize more workers in a short period of time to participate in the construction as soon as possible, undertake the 4 units of the construction task to mobilize more formal workers plus temporary recruitment, therefore, the total number of participants in the construction is still floating. According to incomplete statistics, China construction third bureau has about 700 to 800 people to participate in the construction, wuhan construction about 500 to 600 people, hanyang city about 400 to 500 people, wuhan hangfa builders about 500 to 600 people.
In addition, the temporary headquarters in the vicinity of the site and supporting works are distributed in the form of simple tents, such as electricity, communications, materials, etc.
Reporter scene see in addition to the above 5, many units are building for the vulcan mountain hospital people out of materials. Power supply company is the national power grid caidian district, wuhan branch of China telecom, high energy environment, state science and technology co., LTD., wuhan concrete car AD group, silver source environment, environmental protection technology co., LTD., xing jiang days DingFeng holdings co., LTD., etc. (note: journalist on January 27, all participants to see the unit does not include the whole construction project).
All builder's accommodations have been resolved on site. The workers of the four construction units live mainly in temporary workers' boarding houses; Aid units from afar stay in hotels; Nearby units can either go home or live on the site.
In order to ensure the health of the workers, the new type of lung virus will be blocked off the site, the living area at the entrance, have a person responsible for taking the temperature, disinfection.
Vulcan mountain hospital is scheduled to be completed on February 3. In order to ensure the progress, the site does not stop work 24 hours a day. Under the premise of completing the project schedule, the constructors of each unit shall arrange their own work and rest time. And the design unit staff usually overnight, rest for a while to continue to work, citic design Mr. Zhao told reporters: Vulcan mountain hospital implements the method of designing and constructing at the same time. This is a very special period. Design must go ahead of construction, so everyone is working overtime. .
In order to ensure the normal operation of all Vehicles, sinopec zhiyinhu gas station located near the site is free of charge.
China construction third bureau subordinate units China construction third bureau general contracting company a person in charge, pointing to the distance of the white mobile board room to the reporter: “ Although you see the soil in front of you, the mobile board house is being assembled over there. It is all synchronous operation. It is absolutely no problem to finish on time. .
the boy wore pajamas and drove the Excavator 5 hours late at night and arrived at the construction site
Diggers in pajamas. Wang yingchun/photography
The site of 50,000 square meters is divided into four working areas for synchronous operation, such as land leveling, underground pipeline excavation and laying, anti-leakage construction, and ground hardening. In the first two stages, you need a lot of Excavators. According to a number of workers involved in the excavation work told reporters, around 200 Excavators entered the site before and after the operation. At 1:30 PM on January 27, it was pei Yang's turn to take a rest with the 4-member team. The slight young man from yaoji, huangpi district, wuhan, was wearing messy hair, pajamas and muddy shoes.
Mr. Chen, a workmate beside him, said that at 9 o 'clock on January 23, the night before New Year's eve, pei Yang, who was lying in bed playing with his mobile phone, received news from his partner that excavators and workers were needed at the construction site of vulcan mountain. Four people drove four trailers from huangpi, 24 o 'clock in the morning finally arrived at the vulcan mountain hospital site. After only an hour's rest, they began to work.
& other; When I left, I didn't tell my mom. I didn't tell her until the next day when I was free. Throughout the &; Pei Yang explained. Pei Yang has not yet become a family, and has become a family workmate Mr. Chen said with a smile that the wife has said hello, if finished work home, have to self-isolation.
Mr. Zhang, who has been working in caidian for a long time, did not return to his hometown for the Spring Festival, and learned that vulcan mountain construction site to recruit road cleaners, he immediately signed up, 24 (New Year's eve) to work. Due to a large number of engineering materials Vehicles, mechanical Vehicles in and out of the site, and wuhan to rainy days, in order to ensure vehicle safety, prevent these. Big way & throughout; As they skidded, Mr. Zhang and his colleagues worked with shovels to clear the muddy water from the road. They run on two shifts, and during the day there are about 60 people working on the road.
In addition, several workers were temporarily placed in his rented house.
& other; Thank you for your help. Throughout the &;
& other; No thanks, good salary, 600 yuan a day, daily settlement. Throughout the &; Mr. Zhang answered with a big smile and went on working.
Mr. Cheng, the Truck master of the AD group, jumped out of the cab, and workers immediately unloaded the two Trucks' 120 drainage pipes. Mr. Cheng began to be busy on the first day of the first year. He went back and forth between baishazhou and caidian in wuhan every day. At present, three Trucks are put into operation. We will arrange the quantity of goods according to the needs of on-site construction. If three are not enough, we will send more at any time. Throughout the &; He said.
my daughter, who is 4 months old, drove a private car the wrong way from hunan province to wuhan
Hunan reinforcements retrograde wuhan. Wang yingchun/photography
When disaster strikes, flight is the first response, but there are always people going the wrong way. On the first day of the New Year, Mr. Xiang received the support and mobilization from the chairman of the board. He became a new father, and his daughter had just turned 4 months. This was the first New Year in her life, and he was reluctant to part with her.
& other; We came a total of more than 40 people, we add up the number of people to match the number of cars, drove the private car and set off. Throughout the &; "Mr. Xiang said. His unit, in a high-energy environment, provides anti-seepage engineering and services for the vulcan mountain hospital site.
Mr. Chen, who lives in qiaokou district of wuhan, is working with colleagues to arrange the evacuation of 5G base station equipment. & other; We were the first to build a 5G base station here. He said the 5G base station was built to ensure the operation of the headquarters, and that the next step would be to lay optical cables to ensure data communication after the hospital was completed. In order to keep pace with the construction of the hospital, Mr. Chen and his colleagues worked overtime almost every day.
In addition, in order to make more patients with new pneumonia get hospital beds as soon as possible, located in jiangxia district of wuhan. Raytheon mountain hospital ” It entered the site exploration stage on 26th. Our colleague went to the scene yesterday. Throughout the &; "Said Mr. Chen.
Mr. Cheng just came back from the construction site. He is a staff member of wuhan hangfa. He grabbed a plastic stool and sat down. He has not been back to his home in nanhu, wuhan, for several days. Asked why he was petitioning for battle, he murmured: Do your bit, the people of wuhan are too difficult. .
will not pollute bosom friend lake system
At the beginning of the construction of the vulcan mountain hospital, some members of the public were concerned that the site of the hospital was close to the caidian zhiyin lake. After the hospital was put into use,
Whether sewage and waste will pollute zhiyin lake system.
Participate in seepage engineering construction of Mr. Xiang to the reporter, this need not worry. First of all, after the ground is smooth, two cloth and one film will be used for anti-seepage treatment to avoid soil pollution. In addition, there are special sewage collection equipment, treatment equipment, transfer channels. A large truck was passing by pulling a large green metal container. That's a septic tank. .
On one side of the road near the gate of the wuhan sanitarium, a huge hole has been dug. The space has been levelled and covered with professional anti-seepage materials. Sewage treatment equipment will be installed here. Throughout the &; A designer introduces to reporter.
At 2 o 'clock in the afternoon, in the meeting room on the fourth floor of the sanatorium, the general headquarters is organizing 5 units to hold a meeting on emergency engineering design of vulcan mountain hospital. Now the design plans of different functional areas waiting for construction are being released in groups, collecting problems by profession and focusing on discussion. A staff member of wuhan municipal design institute introduces the design details of their rainwater and sewage pipes to the participants and asks for their requirements. A commander on the scene to the reporter's introduction: This is not the last design meeting. Such meetings are a normal part of our daily work, because we are designing and building at the same time. Throughout the &;
According to the reporter, the hospital after the operation of sewage will be through the pipeline, after the final treatment into the caidian sewage treatment plant.
In a few days, the 50,000 square meter site will have wards, ICU units, reception departments and logistics departments in the eastern and western regions, providing 813 beds for wuhan's new type of pneumonia patients. & other; The 813 beds are the current plan, with some adjustments to the final number as the design is still in progress. Throughout the &; One of the staff involved in the design told reporters.
On the morning of the 27th, premier li keqiang also came to the site to cheer on the people, he shouted three times: ldquo; Come on wuhan! Come on wuhan! Come on wuhan! Throughout the &;
While the vulcan mountain hospital is under construction, the Raytheon mountain hospital is being built in jiangxia, a non-main urban area in the south of wuhan. A number of builders have arrived.
Collated according to customs data,In October 2024, China's import and export trade volume of construction machinery was 48.$4.1 billion,Year-on-year growth of 24.2%。Among:Imports 2.$3.3 billion,Year-on-year growth of 33.1%;Exports 46.$0.8 billion
Guangxi Cummins,Zan 8 Review of past issues
November 20,Party Secretary of Shandong Heavy Industry Group、Chairman Man Shengang Meets with ZF Group Board Members、Peter, Head of Commercial Vehicle Solutions and Industrial Technology·Lyle,The two sides exchanged views on further deepening st
November twenty sixth-The 29th, bauma CHINA 2024 Yingxuan Heavy Industry Booth W5.511 Look forward to your visit. Witness the glory of construction machinery industry with us! ▌Plea
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China