June 04, 2020
On January 29, CCTV reporter from China construction third bureau learned that the wuhan vulcan mountain hospital project site construction is progressing rapidly, the site has nearly 700 management personnel, more than 4,000 workers, all kinds of large mechanical equipment and Vehicle/ 'target='_blank' style='color:blue;'>Transport Vehicles and nearly 1,000 units, 24-hour shift operation into the hospital construction battle.
By the noon of January 29, all the site leveling and backfilling had been completed, about 90% of the concrete casting of the foundation of slab houses had been completed, and more than 300 box-type slab houses had been installed. Meanwhile, slab houses were being assembled off-site and could be directly installed when hoisted to the site. Water, electricity, heating and ventilation, mechanical and electrical equipment and other materials in full place, and synchronous operation.
On January 29, CCTV reporter from China construction third bureau learned that the wuhan vulcan mountain hospital project site construction is progressing rapidly, the site has nearly 700 management personnel, more than 4,000 workers, all kinds of large mechanical equipment and Vehicle/ 'target='_blank' style='color:blue;'>Transport Vehicles and nearly 1,000 units, 24-hour shift operation into the hospital construction battle.
By the noon of January 29, all the site leveling and backfilling had been completed, about 90% of the concrete casting of the foundation of slab houses had been completed, and more than 300 box-type slab houses had been installed. Meanwhile, slab houses were being assembled off-site and could be directly installed when hoisted to the site. Water, electricity, heating and ventilation, mechanical and electrical equipment and other materials in full place, and synchronous operation.
On January 29, CCTV reporter from China construction third bureau learned that the wuhan vulcan mountain hospital project site construction is progressing rapidly, the site has nearly 700 management personnel, more than 4,000 workers, all kinds of large mechanical equipment and Transport Vehicles and nearly 1,000 units, 24-hour shift operation into the hospital construction battle.
By the noon of January 29, all the site leveling and backfilling had been completed, about 90% of the concrete casting of the foundation of slab houses had been completed, and more than 300 box-type slab houses had been installed. Meanwhile, slab houses were being assembled off-site and could be directly installed when hoisted to the site. Water, electricity, heating and ventilation, mechanical and electrical equipment and other materials in full place, and synchronous operation.
On January 29, CCTV reporter from China construction third bureau learned that the wuhan vulcan mountain hospital project site construction is progressing rapidly, the site has nearly 700 management personnel, more than 4,000 workers, all kinds of large mechanical equipment and transport vehicles and nearly 1,000 units, 24-hour shift operation into the hospital construction battle.
By the noon of January 29, all the site leveling and backfilling had been completed, about 90% of the concrete casting of the foundation of slab houses had been completed, and more than 300 box-type slab houses had been installed. Meanwhile, slab houses were being assembled off-site and could be directly installed when hoisted to the site. Water, electricity, heating and ventilation, mechanical and electrical equipment and other materials in full place, and synchronous operation.
On January 29, CCTV reporter from China construction third bureau learned that the wuhan vulcan mountain hospital project site construction is progressing rapidly, the site has nearly 700 management personnel, more than 4,000 workers, all kinds of large mechanical equipment and transport vehicles and nearly 1,000 units, 24-hour shift operation into the hospital construction battle.
By the noon of January 29, all the site leveling and backfilling had been completed, about 90% of the concrete casting of the foundation of slab houses had been completed, and more than 300 box-type slab houses had been installed. Meanwhile, slab houses were being assembled off-site and could be directly installed when hoisted to the site. Water, electricity, heating and ventilation, mechanical and electrical equipment and other materials in full place, and synchronous operation.
Recently,China-An exchange meeting on agricultural cooperation and trade in agricultural products among African countries was successfully held in Changsha, Hunan。From Benin、Burundi、Burkina Faso、Madagascar、Cameroon、More than 100 governments from Senega
Three Autumn Solar terms Points Wait The Autumn Equinox is approaching,Wisdom makes the future —— Trade Fair countdown 2 days!
To celebrate the 75th anniversary of the founding of the People's Republic of China September to October China Central Radio and Television Station On CCTV News Channel、CCTV Voice of China Launched sim
In the process of new product release,Several XCMG loaders equipped with Yuchai engines shine and deliver to custome
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China