June 04, 2020
On January 29, CCTV reporter from China construction third bureau learned that the wuhan vulcan mountain hospital project site construction is progressing rapidly, the site has nearly 700 management personnel, more than 4,000 workers, all kinds of large mechanical equipment and Vehicle/ 'target='_blank' style='color:blue;'>Transport Vehicles and nearly 1,000 units, 24-hour shift operation into the hospital construction battle.
By the noon of January 29, all the site leveling and backfilling had been completed, about 90% of the concrete casting of the foundation of slab houses had been completed, and more than 300 box-type slab houses had been installed. Meanwhile, slab houses were being assembled off-site and could be directly installed when hoisted to the site. Water, electricity, heating and ventilation, mechanical and electrical equipment and other materials in full place, and synchronous operation.
On January 29, CCTV reporter from China construction third bureau learned that the wuhan vulcan mountain hospital project site construction is progressing rapidly, the site has nearly 700 management personnel, more than 4,000 workers, all kinds of large mechanical equipment and Vehicle/ 'target='_blank' style='color:blue;'>Transport Vehicles and nearly 1,000 units, 24-hour shift operation into the hospital construction battle.
By the noon of January 29, all the site leveling and backfilling had been completed, about 90% of the concrete casting of the foundation of slab houses had been completed, and more than 300 box-type slab houses had been installed. Meanwhile, slab houses were being assembled off-site and could be directly installed when hoisted to the site. Water, electricity, heating and ventilation, mechanical and electrical equipment and other materials in full place, and synchronous operation.
On January 29, CCTV reporter from China construction third bureau learned that the wuhan vulcan mountain hospital project site construction is progressing rapidly, the site has nearly 700 management personnel, more than 4,000 workers, all kinds of large mechanical equipment and Vehicle/ 'target='_blank' style='color:blue;'>Transport Vehicles and nearly 1,000 units, 24-hour shift operation into the hospital construction battle.
By the noon of January 29, all the site leveling and backfilling had been completed, about 90% of the concrete casting of the foundation of slab houses had been completed, and more than 300 box-type slab houses had been installed. Meanwhile, slab houses were being assembled off-site and could be directly installed when hoisted to the site. Water, electricity, heating and ventilation, mechanical and electrical equipment and other materials in full place, and synchronous operation.
On January 29, CCTV reporter from China construction third bureau learned that the wuhan vulcan mountain hospital project site construction is progressing rapidly, the site has nearly 700 management personnel, more than 4,000 workers, all kinds of large mechanical equipment and Vehicle/ 'target='_blank' style='color:blue;'>Transport Vehicles and nearly 1,000 units, 24-hour shift operation into the hospital construction battle.
By the noon of January 29, all the site leveling and backfilling had been completed, about 90% of the concrete casting of the foundation of slab houses had been completed, and more than 300 box-type slab houses had been installed. Meanwhile, slab houses were being assembled off-site and could be directly installed when hoisted to the site. Water, electricity, heating and ventilation, mechanical and electrical equipment and other materials in full place, and synchronous operation.
On January 29, CCTV reporter from China construction third bureau learned that the wuhan vulcan mountain hospital project site construction is progressing rapidly, the site has nearly 700 management personnel, more than 4,000 workers, all kinds of large mechanical equipment and Vehicle/ 'target='_blank' style='color:blue;'>Transport Vehicles and nearly 1,000 units, 24-hour shift operation into the hospital construction battle.
By the noon of January 29, all the site leveling and backfilling had been completed, about 90% of the concrete casting of the foundation of slab houses had been completed, and more than 300 box-type slab houses had been installed. Meanwhile, slab houses were being assembled off-site and could be directly installed when hoisted to the site. Water, electricity, heating and ventilation, mechanical and electrical equipment and other materials in full place, and synchronous operation.
Copyright Notice 2002-2026 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China