Fight again! Sany 800-ton Crawler Crane Helps the First Wind Turbine of PetroChina's First Wind Power Project to Lift Successfully

November 29, 2022

Recently,At the construction site of Unit 3 of Ganqing Wind Farm in Jilin Oilfield,The first section weighs 84 tons.,Diameter 5.2 meters,The 22-meter-high tower rises slowly.,The first Wind Turbine of PetroChina's first wind power project was successfully lifted.,TrinitySCC12000TM(SCC8000A)The Crawler Crane is used as the main crane。This marks that Jilin Oilfield has taken a new step from the traditional oil industry to the integration of new energy.。

This project is an important part of the 150000 kilowatt self-absorption wind and solar power project under construction in Jilin Oilfield.,Including 18 Wind Turbines in total,Total installed capacity 7.80 thousand kilowatts,It is estimated that the annual on-grid electricity will be about 26.043.37 million MWh,Annual equivalent full load 3395 hours。

China Petroleum Engineering Construction Corporation is responsible for the construction of the project.,It entered the site construction stage in early August this year.。So far,Foundation has been completed、Pile cap and other construction links,Hoisting conditions are met.。

  

In charge of the main craneSCC12000TMCrawler Crane,Can meet various construction requirement,Wide adaptability and high security。Since going offline in 2019,It has won high recognition from the market with its outstanding performance.。

May 2019,SCC12000TMInstallation of 110 ton Wind Turbine at 140 m height;

June 2019,At the same height,SCC12000TMLifting 3 with a weight of 116 tons.1MWFan;

January 2020,SCC12000TMRefreshing the new height of domestic wind power hoisting,Successfully lifted 162 meters of 3.45 MW wind turbine。

April 2020,SCC12000TMBe shortlisted“China Construction Machinery Product of the YearTOP50”,And obtain“Golden Word-of-mouth Award”。

  

It is understood that,In addition to fan installation,The booster station of the project、High voltage line、The construction of communication system and other supporting facilities is progressing as planned.,It is expected to be connected to the grid by the end of the year.。At that time,Jilin Oilfield will make substantial progress in clean substitution of power self-consumption。

  

In recent years,PetroChina Continues to Strengthen Top-level Design of New Energy,Accelerate the coordinated development of oil and gas and new energy business,Positive layout in the whole industry chain of new energy。Make every effort to promote the precise landing of various projects、Speed up,Strive to achieve green and low-carbon transformation at an early date、High quality development。

Construction Machinery Online

Language Options

E-Mail: alina@global-ce.com TEL: 0086-10-84673349 FAX: 0086-10-84673349
Site: International - China - U.S.A - Russia - France - Spain - Portugal - India - Germany - Saudi Arabia - Indonesia

Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.

Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China